The construction and domestic garbage must be cleaned up in time, and it is not allowed to be piled up at will
.
Case 2: at about 23:00 p.m
.
The main faults of electrical circuit are overload, short circuit and high resistance of wire connection
.
It is understood that six rooms were burnt down
.
Some construction sites rush to work, catch up with the schedule and even carry out construction work in violation of regulations
.
Evacuation passageway and fire truck passageway must be kept unblocked, and shall not be occupied, blocked, closed, or piled up with sundries
.
Case 1 at 07:50 on January 6, 2021, a fire broke out in a high building at the junction of Aoti West Road and kunshun road in Jinan City, Shandong Province
.
A large number of combustible materials such as linoleum, wood and paint are stored and used in the construction site
.
Do a good job of fire safety inspection to prevent the tragedy from happening to the construction site, the common feature is that there are many combustible and flammable materials
.
The fire safety management of key links should be strictly implemented in the construction site: β work with certificates strictly: conduct a comprehensive review on the personnel of electric welding, gas welding, electrician and other special types of work, and put an end to the operation without certificates
.
When the fire rescue personnel arrived, the burning row of prefabricated houses was surrounded by the fire, and the surrounding smoke was diffuse
.
After dozens of minutes of fighting, the fire was put out, and there were no casualties at the scene
.
Some construction sites have set up temporary fire passage, but the passage is full of cement, steel, wood and other debris; even some construction sites have not set up fire passage at all, once there is a fire, the fire engine can not rush to the scene in time, delaying the rescue time
.
Strict examination and approval of hot work: it is forbidden to use open fire in inflammable and explosive places
.
The construction site shall be provided with fire water source according to the regulations, and random sampling test shall be carried out to ensure that the pressure and flow of the pipe network meet the requirements of fire fighting water supply
.
Strict fire separation: the office, living area and operation area of the construction site must be set separately to keep enough safety distance
.
At present, the cause of the accident is under further investigation
.
on December 30, 2020, a board house at a construction site in the economic development zone of Xiangtan City, Hunan Province caught fire
.
It is recommended to read the top ten typical cases of national emergency rescue in 2020 and the top ten typical cases of national production safety accidents in 2020! β source: Beijing fire protection β editor: Zhang Huayue (Intern) β review: Wang quanjun thinks the article is good
.
During the construction, the frequency of fire and electricity is very high, and welding, boiler and other fire operations are very easy to cause fire
.
Winter has always been a fire prone period, especially at the end of the year
.
The excessive current of the line will cause serious heating, which will cause the insulation material to catch fire, generate electric spark, ignite the nearby inflammables, and cause the secondary fire
.
The command center of Jinan fire rescue detachment immediately dispatched 4 fire rescue stations, 7 fire engines and 56 firefighters to the scene for disposal
.
Click “watching” to share.
.
Ignoring fire safety is very easy to cause fire accidents
.
The use and management of inflammable and explosive dangerous goods must meet the requirements of fire prevention, and no leakage is allowed
.
The construction site is densely populated, coupled with the weak fire awareness of workers, cigarette butts are scattered everywhere, leaving a potential fire hazard to the site
.
According to workers at the scene, three liquefied gas tanks are still stored in the board room on fire, and the situation is very critical
.
The cause of the accident was initially determined to be a fire on the roof asphalt of the construction site
.
For the open fire operation such as electric welding, the hot work department and personnel must go through the examination and approval procedures, and implement on-site monitoring and various preventive measures
.