11 strong clauses in the new regulations for temporary electricity use on construction site! Animation teaching video of temporary power construction

Source: Luban union of construction engineering according to the industry standard “technical code for safety of temporary electricity use on construction site (Draft)” recently issued by the Ministry of housing and urban rural development, there are 11 mandatory provisions in the revised new regulation: [01] 3.2.11it is strictly prohibited to install switches or fuses on PE lines, to pass working current, and to break lines

.

[02] 5.2.3 the power supply of generator set must be interlocked with the power supply of external power line, and parallel operation is strictly prohibited

.

[03] 6.2.1 the cable must contain all working core wires and core wires used as protective zero wire or protective wire

.

The five core cable must be used in the cable line of three-phase four wire distribution system

.

The five core cable must contain light blue and green / yellow insulated core wires

.

The light blue core wire must be used as n wire; the green / yellow core wire must be used as PE wire, and mixed use is strictly prohibited

.

[04] 6.2.3 the cable lines shall be laid underground or overhead

.

It is strictly forbidden to set them on the ground, and mechanical damage and medium corrosion shall be avoided

.

The route of buried cable shall be provided with direction identification

.

[05] 7.7.3 when cleaning, inspecting and repairing the concrete mixer, steel processing machinery, technical machinery, shield machinery and other equipment, the switch box must be opened first to cut off power

.

Show the visible power breakpoint and lock the door

.

[06] 9.2.2 the following special places should use safe extra low voltage lighting: 1

.

The power supply voltage should not be greater than 36V for the lighting in tunnel, civil air defense engineering, high temperature, conductive dust, relatively humid or the height of lamps lower than 2.5m from the ground; 2

.

The power supply voltage should not be greater than 24V for the lighting in humid and easily accessible electrified places; 3

.

The power supply voltage should not be greater than 24V for the lighting in particularly humid places, well conductive ground and boilers The power supply voltage shall not be greater than 12V

.

[07] 9.2.5 lighting transformer must use double winding type safety isolation transformer, and autotransformer is strictly prohibited

.

[08] 9.3.10 for the construction in progress and mechanical equipment that affect the passage of aircraft or vehicles at night, eye-catching red signal lights must be set, the power supply should be set in the front of the main power switch on the construction site, and the emergency self provided power supply should be set when the external power line stops power supply

.

[09] 10.1.4 the “preparation, review and approval” procedure must be followed when the organization design of temporary power engineering is prepared and changed, which shall be organized by electrical engineering technicians and implemented after being reviewed by relevant departments and approved by the technical director of the enterprise with legal personality

.

Relevant drawings shall be supplemented when the organization design of power utilization engineering is changed

.

【10】 10.1.5 the temporary power project must be accepted by the preparation, review and approval department and the user, and can only be used after it is qualified

.

【11】 10.3.2 the regular inspection of temporary power engineering shall be carried out according to the divisional and subdivisional works, the potential safety hazards must be handled in time, and the re inspection and acceptance procedures shall be performed

.

The standard text is boring

.

With vivid animation demonstration, the following teaching video comprehensively interprets the “temporary electricity use on construction site” from the following aspects: temporary electricity operators, temporary electricity grounding measures, wire and cable fixation and conduit laying, setting and daily maintenance of distribution box, operation of construction machinery and tools, inspection and use of electrical equipment Acceptance of temporary power project, common illegal operation, treatment of electrical fire, filing management of temporary power data

.

Construction and temporary use of electricity: easy to understand and produce

.

Nanning urban and Rural Construction Committee [production] Nanning construction management office, Nanning Construction Quality Safety Association, Nanning construction accident injury insurance service center, Guangxi cloud Shang Beauty Culture Communication Co., Ltd

.

electromechanical installation official account, ID:zhulongdq, what is the reason why K is small? K Write V in capital? What do BV, BLV, VV and VLV represent? Zero basis can also learn the electrical wiring high-definition color map! Zhulong water supply and drainage ID: zhonggp wonderful excerpt detailed water and electricity installation project delivery standard, take it away quickly! 3 minutes to deal with the relationship between pump head and water in and out! 16 kinds of valve dynamic working principle diagram, worth collecting! Zhulong HVAC ID: zhongnt wonderful excerpt Design Institute HVAC new staff training courseware! Do you know about fresh air system? Public places central air conditioning ventilation system health emergency plan stamp the following original reading, more material!.

.