Another article: the use of socket type and disk buckle scaffold is promoted in construction site

Recently, Haining housing and Urban Rural Development Bureau issued the notice on Further Strengthening the use and management of socket type turnbuckle scaffold in construction projects in our city, another city began to recognize turnbuckle scaffold

.

Towns, streets, investment platforms, construction, construction and supervision units: Recently, there are many construction safety accidents caused by nonstandard erection and lax management of construction engineering scaffolds across the country

.

In order to further strengthen the safety management of scaffold engineering and ensure the safety of people’s lives and property, this paper further strengthens the use of socket type and buckle type scaffolds for Construction Engineering in our city Management requirements are as follows: 1

.

Implementation scope: all housing construction and municipal infrastructure projects within the administrative region of Haining City

.

2、 Implementation time (1) from February 1, 2021, the newly opened government investment projects and state-owned capital investment projects must be implemented as required

.

(2) From March 1, 2021, other projects within the implementation scope of the new construction permit must be implemented as required

.

3、 Relevant requirements (1) if it is really impossible to use socket type steel pipe scaffold due to engineering type, structural type and other reasons, it must be applied by the engineering construction unit, approved by the supervision unit and the construction unit, and reported to the competent department of the industry for registration before using other types of scaffold system conforming to the national and industrial specifications

.

(2) Before the construction of socket type and turnbuckle scaffold, a special construction scheme with complete contents, accurate calculation, pertinence and operability shall be prepared in combination with the actual situation of the project

.

The scheme must comply with the provisions of the detailed rules for the safety implementation of socket type and turnbuckle steel pipe formwork support and scaffold construction in Jiaxing construction project (Trial Implementation) and the safety management of more dangerous divisional and subdivisional projects The regulations (Order No

.

37 of the Ministry of housing and urban rural development) require that the procedures of examination and approval should be fulfilled, and the implementation should be organized after the safety technical disclosure (the special construction scheme of more than a certain scale divisional and subdivisional projects with greater risk should be certified by experts)

.

(3) The quality of components and fittings of various specifications in the socket type steel pipe scaffold must meet the requirements of corresponding specifications and standards

.

For components and fittings entering the site each time, the construction, construction and supervision units shall strictly accept their quality (including steel pipe wall thickness) in accordance with the requirements of relevant specifications or technical regulations

.

The relevant acceptance data shall be recorded in writing and signed by the acceptance personnel for confirmation Before use, sampling inspection shall be carried out under the witness of on-site supervision personnel according to the regulations, and it can only be used after passing the inspection

.

(4) The construction unit shall organize the construction in strict accordance with the approved special construction scheme, and shall not modify or adjust the special construction scheme without authorization

.

If it is necessary to adjust due to changes in design, structure, external environment and other factors, the special construction scheme after adjustment shall go through the examination and approval procedures again according to the original procedure

.

If it needs expert argumentation, it shall organize expert argumentation again

.

(5) The construction unit and the supervision unit shall strengthen the patrol inspection in the process of scaffold construction, and organize the acceptance section by section according to the regulations

.

After the erection is completed, the relevant technical personnel of the construction unit and the supervision unit shall organize the acceptance in time and form the acceptance record

.

(6) It is strictly forbidden to remove the structural members of the scaffold during the use of the socket type steel pipe scaffold

.

The construction unit and the leasing unit shall strictly implement the maintenance and scrapping system, and timely carry out the maintenance

.

It is strictly forbidden to use the components and parts with serious corrosion, deformation, cracks and other non-standard conditions

.

(7) All construction, construction and supervision units should seriously implement the safety production responsibility system, bring the use and management of socket type and coil type steel pipe scaffold into the important management category of enterprise safety production, manage in strict accordance with the requirements of standards, specifications, procedures and relevant documents, and strictly implement the scheme demonstration, technical disclosure and acceptance work

.

The Municipal Bureau of housing and urban rural development will focus on strengthening the supervision and inspection of the use, and the problems found in the inspection will be handled in strict accordance with the relevant provisions

.

Source: Haining housing and Urban Rural Development Bureau zhubaicheng, welcome to pay attention.

.