Luba sea crossing bridge project is one of the key projects of the whole coastal Avenue Project
.
Photo and text: Zhao Longhua editor: Wei Quan reviewed by: Huang Yong reviewed by: Xu Fei self strengthening / dedication / enterprising / inclusiveness of the Sixth Engineering Co., Ltd
.
After the completion of the project, it will become the first long bridge in East Malaysia, connecting with the existing pan Borneo Avenue, which is of great significance to improve the development level of regional transportation infrastructure, facilitate the exchange of personnel and materials, improve the regional transportation pattern, and promote regional integration and economic development
.
The Vice Minister of infrastructure and port development of Sarawak first expressed new year’s blessing to all the staff on site, and required the project construction team to do a good job in epidemic prevention in strict accordance with the standard operating procedures, and deliver the bridge with reliable quality, safety and environmental protection to the people of Sarawak
.
of China Railway Bridge Bureau Group.
.
It is the largest single bridge project under construction in Malaysia
.
The precast segmental gluing construction technology is adopted
.
The total length of the bridge is 4844m, which is composed of 1197.6m south approach bridge + 598.8m main channel bridge + 3047.6m North approach bridge
.
Wu Tao, the project production manager of China Railway Bridge Bureau, accompanied the inspection
.
The project will be officially started on January 7, 2020, with a construction period of 48 months
.
On the morning of February 20, ybdatuk Haji julaihi bin Haji narawi, Deputy Minister of infrastructure and port development of Sarawak state, followed us in blue, Together with the owner, Roland Ting kaswee, general director of coastal Avenue and second trunk road of Sarawak Public Works Department, etc., we went to the site inspection and guidance of Luba sea crossing bridge project in D2B bid section of coastal avenue of Sarawak, Malaysia, China Railway Bridge Bureau
.
The approach bridges on both sides are 50m span continuous girder bridges with 16.3m deck width
.
During the inspection, the general leader of the owner reported the current construction safety, quality and progress of the project to the vice minister
.