Construction of Namibian railway repair project is busy

Slide left and right

.

With the arrival of the Spring Festival, the construction site of Namibian railway restoration project department, which was undertaken by China nengjian Gezhouba Group, was under normal construction, and the construction site of a1s1 section of the main line of the railway was in full swing

.

As of February 14, nearly 30000 cubic meters of ballast have been produced, 4500 cubic meters of ballast have been transported to the site after passing the inspection, 9000 galvanized sleepers have been produced, the first batch of 600 sleepers have been transported to the site, and 119 rails have been welded, which can meet the requirements of 6.5km main line laying

.

On February 12, 22 trains loaded with ballast delivered from nearly 400 km suppliers to randrivers material yard at the construction site

.

All culverts in a1s1 section were cleared, and the 54.9 km embankment bearing capacity test and topographic survey data were submitted

.

On February 13, the ballast transported by train arrived at the material storage yard, and a total of 550 meters of main line ballast cleaning and wood sleeper insertion were completed

.

On the eve of the Spring Festival, due to the shortage of materials affected by the epidemic, the project department sorted out all the work, reasonably adjusted the schedule, increased material suppliers, strengthened the communication with suppliers and engineers, vigorously promoted the mobilization of materials, completed the storage of main materials, and met the schedule requirements

.

On the transportation site, the ballast unloading of 15 train cars and the loading and departure of galvanized sleepers of 3 train cars were completed

.

On the new year’s eve of February 11, the first batch of galvanized sleepers passed the inspection

.