Construction technology project manager and director need face attendance twice a day, invalid within 4 hours! Multi site execution

The site shall be inspected daily

.

If there is no false slip, he shall be deemed not to be on duty! The Department of housing and urban rural development of Qinghai Province has issued the notice of the Department of housing and urban rural development of Qinghai Province on carrying out on-the-job information attendance of key personnel in the construction site of housing construction and municipal infrastructure construction projects

.

The project management personnel attendance work is organized and implemented by the project general contracting enterprise, and supervised by the project engineering supervision enterprise

.

2

.

Real name information collection and certification will be implemented for key positions

.

The notice made it clear: 1

.

1

.

3

.

The Municipal Bureau of housing and urban rural development will circulate a notice of criticism every six months on the projects with the lowest matching rates of project leaders, project managers and construction workers’ wages

.

In the process of project implementation, the construction enterprise shall not change the project manager and key personnel at will, and those who change or withdraw without authorization shall be treated as winning the bid by fraud

.

2

.

The working time of each month shall not be less than 90% of the construction time of this month

.

The site shall be inspected daily

.

Implement the responsibilities of general contracting enterprises

.

4

.

Recently, the Bureau of housing and urban rural development of Zhangzhou City, Fujian Province, announced that the project manager would be included in the municipal “blacklist” due to his long-term absence from duty

.

Improve the daily attendance system

.

The leave of project leader and chief supervision engineer of the construction unit shall be approved by the construction unit

.

2

.

Attendance method: from March 1, 2021, the real name identity authentication and real name attendance system of employees in the construction field of the city will be based on the “electronic fence mobile phone positioning face attendance method”

.

The project manager is on duty

.

4

.

From January 1, 2021, all personnel who enter the construction site (including the construction and supervision project department) of residential construction projects under construction in Guangzhou to engage in the project management work shall register their real names in the management application information platform of construction field in Guangzhou

.

The management personnel of the project department, including the management personnel of professional subcontracting and labor service enterprises, should consciously check on work attendance and accept management

.

3

.

Quality and safety supervisors should strengthen the attendance management of project management personnel

.

The working time of each month shall not be less than 90% of the construction time of this month

.

Full time safety officers perform their duties on duty

.

It was ordered to replace the project manager within 10 working days and complete the change procedures of “project supervision system”

.

4

.

The working time of each month shall meet the requirements of the bidding documents and the contract, and shall not be less than 30% of the construction time of this month

.

3

.

The municipal construction field management application information platform will be used to supervise the attendance of project management personnel, especially the attendance of project leader and chief supervision engineer

.

The attendance of key positions will be checked by face recognition through the attendance channel of “construction workers management service module” on the construction site

.

1

.

5

.

Nantong: the project manager’s on-the-job time every month shall not be less than 80% of the construction time! Nantong Bureau of housing and urban rural development printed and issued the “implementation rules of Nantong construction site management”, which specifies the time of main management personnel performing their duties

.

One of the project manager, technical director and safety officer has no attendance record for two consecutive months or the attendance rate is less than 9 days (40%), and the construction enterprise is put on file for investigation and punishment for suspected illegal behaviors of subcontracting affiliation

.

All kinds of employees in the construction leading city of the whole city must carry out real name identity authentication

.

The chief supervision engineer performs his duties on duty

.

The safety supervisor is on duty

.

In the process of engineering construction, the project manager’s duty performance time shall not be less than 80% of the construction time of this month, and the chief supervision engineer’s duty performance time shall not be less than 40% of the construction time of this month

.

According to the work progress, face recognition attendance management is gradually implemented for other key positions (quality controller, construction worker, equipment manager, crane driver)

.

For the projects whose comprehensive attendance rate for three months or more in a year fails to meet the performance requirements, the local competent department of housing and urban rural construction shall take measures such as ordering the project to stop work for rectification, interviewing the project and enterprise leaders, issuing a notice of criticism and administrative punishment

.

2

.

Jinhua: those who are not on duty should be put on file for investigation! Brush your face twice a day for attendance, and put on record and investigate the illegal behaviors found in the inspection.

.

2

.

Guangzhou: from March 1, the project manager and others will have face recognition attendance every day! Guangzhou housing and Urban Rural Development Bureau issued “notice on strengthening real name attendance of management personnel of housing construction projects in Guangzhou”

.

6

.

We will step up efforts to set up the “e-national column” to ensure full coverage of all projects under construction within our jurisdiction before the Spring Festival of 2021 (February 11)

.

The monthly shift production time shall not be less than 80% of the construction time of this month

.

3

.

The project manager is not on duty for a long time! Several projects are forced to stop work! On duty supervision, more strict! Chengdu: from now on, project managers and directors need to check on work attendance twice a day, which is invalid within 4 hours! On January 18, Chengdu Municipal Bureau of housing and urban rural development issued the “emergency notice on implementing the main responsibility and doing a good job in the management of real name system of employees in the field of construction”, which will take effect from the date of printing and distributing

.

1

.

According to the attendance situation, implement the star Mark Management of monthly attendance of on-site construction project department

.

The person in charge of project safety is on duty

.

If there is a need to change the key positions of personnel, it is necessary to submit relevant supporting materials, with the consent of the construction unit, through the relevant platform for information change

.

Strengthen the management of real name registration

.

5

.

The attendance place is uniformly located in the office area of the general contracting (supervision) project department

.

Each construction general contracting enterprise is responsible for the purchase of the attendance equipment for the personnel of the project management department (access control may not be set), and its attendance data and the real name attendance data of the construction site workers are uploaded to the municipal construction field management application information platform

.

1

.

Nanjing: daily face attendance, exit within 4 hours is invalid! In 2020, Nanjing printed and issued the “management measures for attendance of main personnel on site”: 1

.

Face attendance management is adopted in the construction site, daily attendance is adopted, and the time interval between entering and leaving the site on the same day is more than four hours as effective attendance

.

The project manager, the project director and the project leader of the construction unit must carry out real name attendance on the project site according to the regulations before the project safety supervision is terminated

.

Configure the attendance equipment of the project department

.

Project management personnel attendance management

.

If the competent department of housing and urban rural development does not have a written leave when checking, the person who asks for leave shall be deemed not to be on duty

.

Attendance time: the project manager, project director and project leader of the construction unit of the construction in progress project shall complete the attendance of entering and leaving the site twice according to the requirements, and the on-the-job time shall not be less than 4 hours, otherwise, the system will automatically regard the attendance as invalid

.

Ningxia: if the attendance rate of project manager is less than 40%, the construction enterprise shall be investigated! Those who change personnel without authorization shall be treated as winning the bid by fraud! On September 27, 2020, Ningxia Department of housing and urban rural development issued the notice on strengthening the attendance management of key personnel in housing construction and municipal engineering projects in the whole region, which has stricter regulations on duty performance

.

From March 1, 2021, the project management personnel going in and out of the construction and supervision department of the city’s residential construction projects under construction shall implement the daily attendance system (going in and out of the construction site shall be carried out according to the relevant requirements of workers’ real name attendance)

.

Qinghai: if the project manager asks for leave, he shall be approved by the construction unit

.

The management personnel who do not attend the work or whose attendance is abnormal will be given credit records according to law and regulations

.

3

.

4

.

The local housing and construction administrative department of the project shall guarantee the salary of migrant workers in the next month Special inspection shall be conducted on the payment

.

2

.

The attendance facilities of the project Department of each project site shall be ready before March 1, 2021

.

The monthly attendance days of the project manager shall not be less than 24 days, the monthly attendance days of the project director and the project director of the construction unit shall not be less than 15 days, the monthly attendance days of the project manager shall be less than 12 days, and the attendance days of the project director and the project director of the construction unit shall be less than 10 days

.

5

.

5

.

Leave shall be written and the reasons for leave shall be indicated, and the leave shall be cancelled in time after taking up the post

.

The technical director of the project is on duty

.

Attendance adopts biological (face) recognition method

.