The construction progress of Jian’an Street (Baishazhou avenue to nanhu road) project continues to be delayed

#Baishazhou information learned: Jian’an Street (Baishazhou avenue to nanhu road) project starts from Baishazhou Avenue in the West and ends at nanhu road in the East

.

It successively crosses with Baishazhou Avenue, Fenghuo Road, Yi’an West Road, Beijing Guangzhou railway, Wuxian intercity, Yi’an Road, hongqicun road and nanhu road, with a total length of 1220.18m and a red line width of 40-60m

.

The construction mode of “road + overpass Beijing Guangzhou Railway” is adopted

.

Due to the complex working procedure of swivel bridge, site restrictions and quality requirements, the construction party has optimized the inverted construction period for many times, and plans to complete the main project before the end of December 2021, which is ready for traffic

.

At present, the construction unit is in intensive construction

.

Schematic diagram of Jian’an Street “Baishazhou information citizen: about the completion time of Jian’an Street (Baishazhou avenue to nanhu road)? Wuhan Urban Investment reply: due to the demolition of Ping’an villa, the construction of Jian’an street was suspended for about two years

.

The Ping’an villa, which affected the construction, was demolished at the end of September this year

.

Due to the complex process of swivel bridge, site restrictions and quality requirements, the construction party optimized the inverted construction period for many times, and planned to complete the main project before the end of December 2021, which was ready for traffic

.

At present, the construction unit is in intensive construction

.

(2) construction drawing of West extension line of Jian’an street / information provided by owners of Baishazhou: Baishazhou information source: Wuhan message board | Baishazhou information exchange group.

.