What can construction technology do in 113 days? Top three hospitals are fully capped!

As a medical remedy board project in Wuhan, it is designed according to the principle of “combining peacetime with wartime”, including 200 beds for infectious diseases and 800 beds for ordinary patients, and is usually used as a class III a general hospital The epidemic situation can be quickly converted into an infectious disease treatment hospital with thousands of beds

.

The acceleration of the project construction was 10 days, the earthwork was 200000 cubic meters, the construction of 5510 piles was completed in 28 days, and the construction of the first single building started in 83 days Four days after the main structure of the infected building was capped, the administrative and logistics building was capped again for 113 days, and the main structure was fully capped

.

When the epidemic situation occurs, the corridor can be quickly controlled to play a barrier role

.

With a total construction area of 207000 square meters, the design of 1000 beds, the highest single 13 storey only 113 days, the main structure fully capped! On January 25, Wuhan Tongji Aerospace City hospital project, one of the seven major public health projects of “five districts and two hospitals” in Wuhan, undertaken by the general contracting company of China Construction Third Engineering Bureau, refreshed the limit construction period of “Wuhan speed” for hospital construction

.

The acceleration of the construction was decisive at the beginning, and the sprint was at the beginning of the construction

.

In the fourth quarter of 2020, the monthly output value exceeded 100 million yuan

.

The whole line combat project is large in volume, complex in design and tight in construction period

.

There are smart ideas for “combining peacetime with wartime”

.

The overall layout of the hospital area adopts the general layout of “three districts and two axes”

.

Each area is separated by a wide green isolation belt and connected with each other by a corridor

.

After the completion of the project, it will effectively increase the population Strengthen the industrial supporting function of Wuhan National Aerospace industry base, effectively improve the treatment ability of Wuhan city to deal with public health emergencies, do not fear the limit time limit to build high-quality projects, adhere to the ingenuity of large enterprises to create value, explore the growth secret of the project, decode the construction code behind the rapid construction of the project, please turn the mobile phone to watch, build quality projects with the limit time limit, and help high-quality performance with ingenuity

.

The infection area, comprehensive medical area and administrative logistics area are clearly arranged in turn

.

The construction site is divided into four large work areas and 46 small work areas At the peak of the war, on the 80000 square meter working face, more than 2000 builders entered the construction site in 24 hours, with 5000 tons of materials, 20000 tons of steel bars, 160000 cubic meters of concrete and 430000 cubic meters of formwork

.