Review whether the safety measures in the construction organization design comply with laws, regulations and mandatory standards
.
③ The content and scope of the subcontractor
.
The main raw materials, components, fittings and equipment required for the project shall be identified by the supervision unit and submitted for approval
.
The quality, technical management system, quality assurance system, system and block diagram, safety production management system and block diagram and system of the project department
.
② Acceptance content: A
.
The organization design approval procedures are complete, and whether the safety measures before construction are in place
.
c
.
For concealed works, the construction unit shall fill in A4 “application form for inspection” and report it to the supervisor one day in advance
.
according to the actual arrival and operation records of full-time safety officers of the construction unit
.
The construction contractor shall conduct the level by level safety disclosure, including the general safety disclosure for the subcontractor by the general contractor, the safety operation specification disclosure for the operators according to the type of work, and the safety technical disclosure for the divisional and subdivisional works in the construction process
.
④ Qualification certificate and work license of full-time management personnel and special operation personnel
.
③ Acceptance results: A
.
Review the qualification of the general contractor and the personnel composition of the project management organization, confirm the allocation of full-time safety officers of the contractor, and review their qualification
.
The unified table is adopted for the supervision data (note for Douding Construction: it is determined according to the local actual situation)
.
Before the project starts, there should be written records for the disclosure and joint review of construction drawings, and after the disclosure, the meeting minutes should be sorted out and filled in, which should be approved by the design, supervision and construction unit The construction can be started only after countersignature
.
Eight dead and one wounded! The general manager of the supervision / construction unit has been arrested! Secretary for housing and urban rural development / deputy county magistrate and other 20 people were prosecuted! 3
.
Qualification certificate of special operation personnel (electrician, scaffolder, welder, mechanical operator, tower crane driver), business license of construction enterprise, qualification certificate and safety production license
.
Safety acceptance before starting ① acceptance conditions: a
.
6
.
b
.
② Factory certificate, technical certificate or quality guarantee
.
The construction unit shall fill in the A2 construction organization design (scheme) application form and submit it to the supervision unit
.
Inspection of temporary living facilities and electricity safety, basic site layout, inspection of qualification certificate or relevant data of construction machinery entering the site
.
The construction unit shall use qualified mechanical equipment, construction machine accessories, materials required for safety facilities and personal safety protection articles
.
The construction contractor shall establish and improve the Safety Production assurance system on the construction site, including: safety production management organization, safety production rules and regulations, safety production education and training system, safety production operation regulations, etc
.
The construction organization design and construction scheme must be completed by the construction unit on the basis of complete self-examination procedures of the construction unit (i.e
.
4
.
The results of Surveying and setting out shall be submitted for approval, and the post certificates of full-time surveying personnel of the contractor and the verification certificates of measuring equipment shall be submitted for approval
.
③ Sampling test is needed before use
.
7
.
4
.
The construction safety assurance system has been established, perfected and put into operation
.
6
.
① Production license, permission and record certificate of raw materials, components and accessories
.
10
.
The corridor was frozen, and the owner warmed the corridor
.
④ The main raw materials, components and equipment, if necessary, should go to the manufacturer site inspection
.
General schedule, monthly schedule and basis of approval form, main data: template installation, template removal, raw materials of reinforcement, reinforcement processing, reinforcement installation, reinforcement installation, concrete construction, inspection lot of cast-in-place structure appearance size deviation, concealment, divisional and itemized data and approval form, concrete opening appraisal, concrete pouring application, concrete formwork removal application form Materials: formwork acceptance record, scaffold acceptance record, temporary electricity acceptance record, construction machinery acceptance record, tower crane acceptance record, template removal application report, the data that the construction unit needs to report to the supervisor for approval before the project starts
.
7
.
In the process of construction, no matter who puts forward the engineering change, C2 “engineering change order” must be filled in according to the requirements, and the construction can only be carried out after it is countersigned
.
② Performance of subcontractors
.
c
.
9
.
11
.
the construction organization design has been compiled and reviewed
.
with the signature of the compiler, the technical director of the construction unit and the public examination of the construction unit)
.
meet the requirements, allow the project to start, 1, 23 people died, 19 people were injured! Collapse, is the “killer” on the construction site 2
.
From now on, all returnees must hold the qualified nucleic acid report within 3 days before entering the construction site! Another article 4, 3 dead and 4 injured! The person in charge of the site and the supervisor were arrested! Project manager, director and chief engineer of Design Institute have their registration certificate revoked! 5
.
Examine the qualification of professional and labor subcontracting units
.
Including: ① business license, enterprise qualification certificate and construction license of special industry of the subcontractor
.
2
.
Construction organization design and construction scheme approval
.
5
.
The reason was: “the designer is from the South…” Click “watching” to let your friends know.
.
d
.
Safety production agreement, safety education for team members and disclosure records
.
No concealed construction can be carried out without acceptance and signature on the inspection record of concealed works
.
Safety report and quality supervision
.
The subcontractor selected by the general contractor shall submit A3 “subcontractor qualification application form” and relevant information of the subcontractor
.
The construction unit shall submit the quarterly schedule, monthly schedule, weekly schedule, as well as the relevant material and equipment demand plan, and fill in A1 construction schedule approval form
.
1
.
The approved construction organization design, construction scheme and construction unit shall seriously implement them in the construction process, and shall not change them at will
.
b
.
2
.
8
.
Great summary! 6
.
Technical scheme category: construction organization design, special safety construction scheme, safe and civilized construction scheme, construction site emergency rescue plan, bid winning notice, contract, drawing joint review, geological survey report, design change survey verification data: Engineering positioning survey and setting out records, line inspection records, materials, equipment, components and accessories quality certification documents: certificate, factory inspection report And retest report, commercial concrete qualification, commercial concrete data, other material certificate, record certificate and application form inspection test data: steel bar test welding, finished product welding retest report, test block test report and other test data, material laboratory qualification application form commencement report: commencement application form, commencement report, project overview table, construction management personnel list (management personnel professional qualification certificate) Written by: Project Manager, quality inspector, safety officer, constructor, technical director, material officer, tester, and project manager safety qualification certificate)
.
When the conditions for the commencement of the project are met, the general contractor shall fill in A1 project commencement / resumption report form and submit it to the supervisor for approval and signature
.
If necessary, they shall be re submitted for approval
.
8
.
3
.
5
.
Living area and site safety design have been established and completed
.
The qualification of electrician, welder, scaffolder, crane operator, tower crane driver, commander and other special work personnel shall be reviewed once every two years and shall not be used beyond the time limit
.
The construction contractor shall prepare the special safety construction scheme for the subdivisional works with high risk
.
9
.
3
.