Recently, Putian housing and Urban Rural Development Bureau issued a document to implement the notification and commitment system of construction permit commencement conditions
.
For a new social investment simple low-risk engineering construction project in the administrative region of the city, the housing and construction department can directly issue the construction license only by submitting the application form, the approval document of construction land and the “letter of commitment with commencement conditions”
.
Housing construction and municipal infrastructure projects with project investment less than 1 million yuan (including 1 million yuan) or construction area less than 500 square meters (including 500 square meters) need not apply for construction license
.
The construction drawing examination of social investment simple and low-risk engineering construction project is no longer the precondition of construction permit
.
The first is to deepen the reform of project approval system
.
For a new social investment simple low-risk engineering construction project in the administrative region of the city, the housing and construction department can directly issue the construction license only by submitting the application form, the approval document of construction land and the “letter of commitment with commencement conditions”
.
Compared with the past, the number of application materials can be reduced by 7, or 70%, and the approval time can be shortened by 2.5 days, or 83.3%
.
Second, strengthen post approval supervision
.
After making the commitment, the construction unit shall submit the corresponding materials within 7 working days
.
If the materials are not submitted, the submitted materials do not meet the requirements and cannot be supplemented or corrected, or the legal conditions are not met through supervision and verification after examination and approval, the administrative examination and approval decision will be revoked according to law
.
The third is to optimize the application mode of construction permit
.
Housing construction and municipal infrastructure projects with project investment less than 1 million yuan (including 1 million yuan) or construction area less than 500 square meters (including 500 square meters) need not apply for construction license
.
At the same time, the construction drawing review of social investment simple low-risk engineering construction project is no longer a prerequisite for the construction permit.
.