61
.
The quality supervision organization of the government inspects the establishment of the quality assurance system of all parties participating in the construction of the project, which belongs to the content of () quality supervision
.
A
.
construction process B
.
completion acceptance stage C
.
before the commencement of the project D
.
archives establishment stage C
.
before the commencement of the project, () the key point of inspection is the quality behavior of all parties involved in the project construction
.
The main contents of the inspection are: (1) to check the establishment of the quality assurance system of all parties involved in the construction of the project, including the organization, quality control scheme, measures and quality responsibility system; (2) to review the engineering operation qualification certificates of all parties involved in the construction and the qualification certificates of relevant personnel; (3) to examine whether the construction administrative procedures required by the construction procedures before the commencement of construction are complete; (4) to examine the construction organization design, () supervision planning and other documents as well as the approval procedures; (5) to keep the records of the inspection results
.
[source] 2z104052 implementation of construction quality supervision by the government p18262
.
According to the standard of civilized construction site, the construction site must be set up with “five plates and one map” (), in which “one map” refers to ()
.
A
.
construction progress horizontal chart B
.
large machinery layout location chart C
.
construction site traffic organization chart D
.
construction site layout plan [answer] d [analysis] “five cards and one map”, namely project overview board, () management personnel list and supervision telephone board, fire protection (fire responsibility) board, safety production board, civilized construction board and construction site plan
.
[source of test points] 2z105041 requirements for civilized construction on construction site P215 63
.
Among the following contract pricing methods, () has the lowest risk to the contractor
.
A
.
unit price contract B
.
cost plus remuneration contract C
.
fixed total price contract D
.
variable total price contract B
.
cost plus remuneration contract is also called cost compensation contract, () with this kind of contract, the Contractor does not bear any risk of price change or quantity change, which is mainly borne by the owner, which is very unfavorable to the owner’s investment control
.
[source of test site] 2z106033 cost plus remuneration contract p258 64
.
According to the quality management system basis and terminology, the unqualified engineering products related to the specified use are called ()
.
A
.
common quality problems B
.
quality defects C
.
quality problems D
.
quality accidents B
.
according to the terminology interpretation of quality management system basis and terminology (GB / t19000-2016), all engineering products that do not meet the quality requirements are called quality defects; those related to the intended or specified use are called quality defects
.
In the construction of the main structure of the construction project, () the frequency of supervision and inspection arranged by the government quality supervision organization is at least ()
.
A
.
once a week B
.
once every ten days C
.
once a month D
.
once a quarter C
.
The supervision organization shall carry out irregular inspection on the whole construction process of the project according to the supervision scheme, () the supervision and inspection shall be arranged monthly for the construction of the foundation and main structure stage
.
[source of test site] 2z104052 implementation of construction quality supervision by the government p18266
.
According to the classification of risk factors, () the risk caused by insufficient fire prevention facilities at the construction site belongs to () risk
.
A
.
economy and management b
.
organization C
.
engineering environment D
.
technology a [analysis] economic and management risks, such as: (1) project fund supply conditions; (2) contract risk; (3) availability and quantity of site and public fire prevention facilities; (4) accident prevention measures and plans; (5) personal safety control plan; and; (6) information security control plan, etc
.
[source of test site] 2z101062 type of construction risk P39 67
.
A
.
the latest start time is equal to the minimum value of the latest start time minus the duration of each tight work; B
.
the latest start time is equal to the maximum value of the latest start time of each tight work; C
.
the latest start time is equal to the minimum value of the latest start time of each tight work; D
.
the latest start time is equal to the maximum value of the latest start time minus the duration of each tight work [answer] a [analysis] this question examines the concept of the latest start time
.
() the latest start time (lsi-j) refers to the latest time when the work I-J must start without affecting the completion of the whole task on schedule
.
The latest start time is equal to the latest finish time minus its duration: lfi-j = lfi-j-di-j
.
[source of test site] type and application of 2z103032 project network plan p138 68
.
Claim events refer to all kinds of events that the actual situation does not conform to the contract provisions and () eventually causes () changes
.
A
.
quality and cost B
.
safety and construction period C
.
construction period and cost D
.
standard and information C
.
claim events, also known as interference events, () refers to all kinds of events that make the actual situation inconsistent with the provisions of the contract and eventually cause changes in construction period and cost
.
[source of examination] 2z106051 basis and evidence of construction contract claim
.
A
.
quality plan B
.
process management C
.
PDCA cycle D
.
quality manual [answer] a [analysis] the operation of construction quality assurance system, () should take quality plan as the main line, process management as the center of gravity, according to the principle of PDCA cycle, according to the steps of planning, implementation, inspection and treatment
.
Establishment and operation of construction quality assurance system of 2z104021 project p158 70
.
A construction project was shut down due to the owner’s temporary design change, () the Contractor’s workers idled for 8 working days, and the idling cost was 300 yuan / working day; The contractor rents two idle shifts of the excavator: the rental fee of the excavator is 1000 yuan / shift, the power fee is 160 yuan / shift, and the contractor owns two idle shifts of the dump truck, the depreciation fee of the truck is 400 yuan / shift, and the power fee is 200 yuan / shift
.
The cost that the contractor can claim from the owner is () yuan
.
A.5200 b.4800 c.5400 d.5800 [answer] a [analysis] reimbursable expenses: labor cost = 300 × 8 = 2400 yuan; rental machinery cost = 1000 × 2 = 2000 yuan; self owned machinery cost = 400 × 2 = 800 yuan
.
2400 + 2000 + 800 = 5200 yuan
.
[source of test site] 2z102035 claim and on-site visa P91.
.