Danzi North Road project construction progress daily report-2021.04.23

1、 Site construction operation (1) site machinery and equipment in work area 1 of project: 2 cement mixing piles, 1 cement mixing vertical tank, 1 generator, 1 excavator and 4 new energy dump trucks; Site construction content: 50 cement mixing piles are completed at mileage K0 + 150; 46 cement mixing piles were completed at mileage K0 + 250; 56 cement mixing piles were completed at mileage K0 + 690; Reinforcement is installed on the bottom plate of communication cable pipe gallery at mileage K0 + 060

.

K0 + 200 cement mixing pile construction K0 + 240 cement mixing pile construction (2) site machinery and equipment in the second work area of the project: 5 cement mixing pile machines, 6 excavators, 6 new energy dump trucks, 1 bulldozer and 1 roller; Site construction content: the excavation of foundation pit of rainwater tank culvert at mileage K1 + 846 is 550m ³, 86m gravel cushion for box culvert foundation backfill ³、 6

.

Installation of bottom slab reinforcement for box culvert; Y84-y80 rainwater well is installed with cover plate, y68-y71 subgrade is backfilled and compacted in layers with 400m earthwork ³: Excavation of foundation trench of w104-w105 sewage pipe: 18m, earthwork: 350m ³, Base backfill graded gravel cushion; Excavation of foundation trench for rainwater pipeline of y142-y143 section: 18m, earthwork: 350m ³; 140 cement mixing piles have been completed in the section K1 + 940 ~ K2 + 370 of Shenzhen No.20 senior high school

.

K1 + 835 Box Culvert Reinforcement installation, K2 + 300 sewage pipe backfill (3) site mechanical equipment of the third work area of the project: 1 cement mixing vertical tank, 1 cement mixing pile machine; Site construction content: none( 4) Mechanical equipment of temporary construction site of project department: 1 excavator, 1 bulldozer, 1 sprinkler; Site construction content: none

.

2、 Safe and civilized construction (1) morning class meeting (2) evening class meeting (3) civilized construction      Safe and civilized construction inspection (1)         Inspection of safe and civilized construction (2)     3、 Acceptance, application and inspection of equipment and materials     Material stone powder and stone entering the site  1000 × one thousand and two hundred × 200 well block and accessories mobilization note: Materials mobilization of Danzi North Road today  1000 × one thousand and two hundred × There are 6 200 wells, Φ1000 × There are 6 200 shafts, Φ1360 × There are six 120 cover plates

.

Stone powder 36m ³, Stone 36m ³。 4、 No major events occurred

.

5、 Tomorrow’s construction schedule work area I: Construction of cement mixing pile machine for mileage K0 + 170, K0 + 250 and K0 + 690 sections; The foundation of communication cable pipe gallery at mileage K0 + 060 is installed with reinforcement; Two excavators, three cement mixing pile machines and one excavator were put into operation

.

Second work area: Construction of cement mixing pile in section K1 + 940 ~ K2 + 370 of Shenzhen No.20 senior high school; W104-w105 sewage pipe installation and layered backfill stone powder tamping; The subgrade of y68 ~ y70 rainwater pipe is backfilled layer by layer, and y66 rainwater pipe and well seat are installed; Excavation and installation of foundation trench for y140-y143 rainwater pipeline; The foundation pit of drainage box culvert at mileage K1 + 850 is excavated and backfilled with gravel base, and the bottom slab reinforcement of 6 × box culvert is installed; 5 cement mixing pile machines, 5 excavators, 4 new energy dump trucks and 1 road roller were put into operation

.

Third working area: none

.

Source: Tianjian Danzi North Road Project Department information release center editor: Danzi North Road Project Department office proofread by:.

.