Construction organization design and construction scheme are inseparable
.
No matter how to prepare the construction scheme, no matter what form it is, it must be carried out under the overall planning and overall deployment of the construction organization design, which is an indispensable part of the construction organization design
.
Even if it is inseparable, there is still a great difference between construction organization design and construction scheme
.
It is hoped that the new “xiaobairen” will not confuse them
.
First, the concept is different
.
The construction organization design is the basic technical and economic document to guide the construction preparation and implementation of a proposed project
.
It is the construction preparation work and the whole construction process of a specific proposed project (single project or unit project), in terms of manpower and material resources, time and space, technology and organization In terms of organization, making a comprehensive and reasonable plan and arrangement that meets the requirements of good, fast, economical and safety is the analysis of a construction method in unit project or sub project
.
It is the technical and economic analysis of the labor, materials, machinery, cost and construction period consumed in the construction process under the condition of reasonable organization, so as to adopt new technology and choose from them For some construction difficulties and key divisional and subdivisional works in engineering projects, the optimal scheme needs to prepare special construction schemes
.
Second, the compilation purposes are different
.
The construction organization design is the strategic deployment of a project, which is a comprehensive programmatic document for the overall situation of the project
.
It is required to be scientific and instructive, highlight the word “organization”, and select methods of manpower and material resources in construction, time and space Careful arrangement of the layout of the workshop is macro management
.
The documents are prepared according to the contract, design drawings and various specifications, standards, regulations and documents
.
The guidance is to select and define the construction method according to the requirements of quality objectives, the actual requirements of the owner and the design
.
The construction scheme is based on the construction organization design for a certain sub project It will make a detailed deployment of the materials, machines and tools, personnel and technology of this sub project to ensure the feasibility and pertinence of the quality requirements and the requirements of safe and civilized construction, and meet the construction and acceptance specifications
.
3
.
The compilation objects are different
.
4
.
The key points are different
.
5
.
The starting point is different
.
The construction organization design starts from the perspective of the project decision-making level It is the documentary reflection of the decision-maker’s will, more reflecting the principle of scheme determination, how to determine the construction method through multi scheme comparison
.
From the perspective of project management, it is the refinement of construction method, reflecting how to implement, how to ensure quality and how to control safety
.
From the perspective of operation level, it reflects the details of operation With the construction organization design, it contains a wide range of documents, involving all aspects of engineering construction, from the project organization arrangement, construction scheme selection, reasonable arrangement of construction sequence and schedule, effective selection of construction site, optimal allocation and saving use of human, material, financial, technical and other production factors, it coordinates all aspects of work, the construction is planned, rhythmic, and can ensure the quality of construction Quality, progress, safety, to achieve good economic, social and environmental benefits of the construction scheme, it is to guide the implementation process of a specific division, sub project construction, the preparation content usually includes the project overview, construction preparation, main construction methods, quality, safety control and environmental protection and other aspects
.