Longgang District Hospital of traditional Chinese medicine medical complex project construction general contracting project (bid 2) project daily report on April 14, 2021

1、 Daily temperature measurement

.

3

.

Site construction and inspection 1

.

Daily pre shift education

.

2

.

Acceptance and formwork installation of the north half of the second supporting beam on the second floor

.

3

.

On April 14, 57 vehicles were unearthed, with a total of 10206 vehicles, totaling 127575 square meters

.

4、 Follow up construction plan 1

.

Construction of the second supporting beam on the west side

.

2

.

The second layer of stonework is broken

.

3

.

Outward transportation of the second layer earthwork

.

5、 There is no need for the owner to coordinate

.