1、 Daily temperature measurement
.
3
.
Site construction and inspection 1
.
Daily pre shift education
.
2
.
Acceptance and formwork installation of the north half of the second supporting beam on the second floor
.
3
.
On April 14, 57 vehicles were unearthed, with a total of 10206 vehicles, totaling 127575 square meters
.
4、 Follow up construction plan 1
.
Construction of the second supporting beam on the west side
.
2
.
The second layer of stonework is broken
.
3
.
Outward transportation of the second layer earthwork
.
5、 There is no need for the owner to coordinate
.