According to the standard construction contract, the supervisor’s responsibility in the construction preparation stage is ()
.
A
.
Send the notice of commencement to the contractor unconditionally at the time specified in the special conditions; B
.
send the notice of commencement to the contractor 15 days before the commencement date; C
.
approve or request to modify the construction schedule submitted by the contractor; D
.
organize the preparation of the construction “contract schedule”; C
.
This question examines the responsibilities of the supervisor
.
Option B, with the consent of the employer, the supervisor shall issue a notice of commencement to the contractor seven days before the commencement date; option D, the construction schedule approved by the supervisor is called “contract schedule”..
.