2Z102040 Construction cost management and construction cost planning )。( Only the total reserve funds are considered for the whole project
.
On the basis of analyzing the risks of each sub project, the reserve funds should be considered only for part of the sub project
.
The total reserve funds should be considered for the whole project, and the appropriate unpredictable expenses should be arranged in the sub project
.
Without considering the reserve funds of the whole project, the construction enterprises should consider them uniformly
.
6, The curve in line with the change law of construction plan cost is (a)( Among the following construction cost planning indicators, the quality indicator is (a)( 2013 real topic) a Design budget cost plan reduction rate B Planned unit project cost C Design budget cost plan reduction D Through strengthening the management of construction quota and construction task list, the consumption of live labor and materialized labor can be controlled, which belongs to (b) of construction cost management measures( 2013 real topic) a technical measures B
.
Organizational measures C
.
Economic measures D
.
Contract measures 9
.
Setting up full-time safety officers on the construction site is the (a) guarantee measure in the construction safety assurance system( A
.
organization B
.
Technology C
.
System D
.
Input 9
.
What’s right about the difference among competitive cost plan, guiding cost plan and implementing cost plan( D )。( A
.
the guiding cost plan is the construction budget cost plan in the project construction preparation stage, which is more detailed
.
B
.
the implementing cost plan is the budget cost plan in the project manager selection stage
.
C
.
the guiding cost plan is based on the project implementation plan
.
D
.
the competitive cost plan is the estimated cost plan in the project bidding and contract signing stage, 10
.
It is the basis for construction enterprises to establish the responsibility system of construction project cost management and carry out cost control and accounting( D )。( 2014) A
.
construction cost forecast B
.
construction cost analysis C
.
construction cost assessment D
.
construction cost plan( B )。 ( Construction cost refers to the expenses of the project entity consumed in the construction process B
.
Construction cost management is to take corresponding measures to control the cost within the scope of the plan and save the cost as much as possible under the condition of ensuring the construction period and meeting the quality requirements C
.
Construction cost forecast is to prepare the production cost, cost level and cost reduction of construction project in the form of currency in the planning period Written plan of cost reduction and cost reduction measures D
.
On the basis of construction cost accounting, construction cost assessment is to evaluate the cost formation process and the factors that affect the cost rise and fall In order to find the way to further reduce the cost 12
.
Among the following construction cost management measures, the technical measures are( D )。( 2013 (a true topic) A
.
Strengthen the management of construction task list B
.
Work out construction cost control plan C
.
Seeking claim opportunities in the construction process D
.
Determine the most suitable construction machinery scheme 13
.
Among the following measures for construction cost management, those belonging to organizational measures are( D )。( The first real topic of 2012 (a) Determine the best construction scheme B Risk analysis of construction cost management objectives, and develop preventive measures C, select the appropriate contract structure D Strengthen the management of construction quota and construction task list, control the consumption of activities and physical and chemical activities 14
.
A construction contractor decomposes the total target cost of the expressway project it undertakes into bridge engineering, tunnel engineering cost, road engineering cost and other sub items, and prepares the corresponding cost plan
.
This is by( B ) Prepare construction cost plan( Cost composition of a B project composition C project category The key to making the cost plan of construction project is to determine the cost( C )。( The first building in 2012 A
.
Budget cost B
.
Average cost C
.
Target cost D
.
Actual cost 25
.
As for the statement of using time cost cumulative curve to prepare construction cost plan, the correct one is (c) (2015 real topic) A
.
all work starts late according to the quantity, which is not good for saving money; B
.
all work starts early according to the quantity, which is good for saving money; C
.
All work starts early according to the quantity, The guarantee rate of project completion on schedule is reduced
.
D
.
the project manager controls the cost within the planned scope by adjusting the earliest time of key work
.
30
.
The correct statement about the relationship among construction image progress, output value statistics and actual cost is (a) (real topic of 2015) A
.
construction image progress, output value statistics The quantities on which the actual cost is based should be the same
.
B
.
the quantities on which the construction image progress and output value statistics are based are the same, but different from the quantities on which the actual cost is calculated
.
C
.
The quantities on which the construction image progress, output value statistics and actual cost are based are different
.
D
.
the quantities on which the output value statistics and actual cost are based are the same, However, it is different from the quantity (2) multiple choice question on which the visual progress calculation is based )。( A
.
tender documents B
.
Construction cost forecast C
.
contract signed D
.
Construction organization design or construction scheme E
.
enterprise quota and construction budget 4
.
According to cost composition, construction cost is divided into labor cost, material cost and cost( AD )。( 2013 real topic) a Management fee B Measure fee C Estimated cost D Construction machinery usage fee E Overhead 5
.
About the construction cost control, what is correct( ABDE )。( Contract measures should be adopted to control the construction cost, which should include the whole process from contract negotiation to contract termination
.
Construction cost control should run through the whole process of the project from bidding stage to completion acceptance
.
The current cost control procedure does not conform to the principle of dynamic tracking control
.
Contract documents and cost plan are the objectives of cost control
.
E
.
cost control can be divided into advance control, cost control and cost control 7
.
When the construction cost plan is prepared according to the construction schedule, if all the work is arranged according to the earliest start time, the impact on the target control of the project is significant( AC )。( The monthly cost plan of a project is shown in the figure below
.
If the actual cost in June and July is 7 million yuan and 10 million yuan, the actual cost in other months is the same as the plan, What’s right about the statement of cost deviation( BCD )( The cumulative value of planned cost at the end of the seventh month is 35 million yuan
.
B
.
the cumulative value of planned cost at the end of the sixth month is 25.5 million yuan
.
C
.
The cumulative value of planned cost at the end of the sixth month is 26.5 million yuan
.
D
.
the cumulative value of actual cost at the end of the seventh month is 35.5 million yuan.
.