Bidding conditions the construction of the project has been approved by the administration of Haikou Jiangdong new area with the Haijiang Dongju letter [2021] No
.
968
.
The bid inviting party (project owner) is Haikou Urban Construction Group Co., Ltd
.
(construction agent)
.
The construction fund is from the government investment, and the project investment ratio is 100%
.
The project has met the bidding conditions, and now the public bidding is carried out for the construction of the project
.
2
.
Project overview and scope of bidding 2.1 construction location: Haikou 2.2 construction content and scale: Maiya River Wetland Park and its surrounding areas have perfect functions
.
The total planning and construction area is about 351440m2 (scattered in the construction area)
.
The main construction contents include: wall painting, changing “white to black” of Diding Road, Park Logo wall, science popularization display system, scientific research monitoring facilities Plant replanting and night scenery decoration around the main tour line
.
2.3 planned construction period: 20 calendar days, defect liability period: 730 calendar days
.
2.4 scope of bidding: general construction contract (see the construction drawings and bill of quantities provided by the bidder for details) 2.5 bidding control price: 6938899.16 yuan 2.6 quality requirements: qualified 3
.
Qualification requirements of the bidder 3.1 The bidder is required to have independent legal personality and effective safety production license, It has the qualification of grade III or above for general contracting of municipal public works approved and issued by the construction administrative department, and the single contract amount of a municipal public works completed or under construction within the past three years (from April 1, 2018 to now) from the deadline for the bidder to submit the bidding documents has reached 4 million yuan (including) or more (supporting materials: provide the contract agreement, The time of construction in progress shall be subject to the time of signing the contract; If the project is completed, the completion acceptance certificate shall be provided
.
The time shall be subject to the completion acceptance time, and the original copy shall be verified)
.
Performance, and has the corresponding construction ability in personnel, equipment, capital, etc, The person in charge of the project (Project Manager) to be assigned by the bidder shall have the qualification of registered constructor of grade II (including higher level) of municipal public works specialty registered in the unit, and obtain the safety production assessment certificate (B certificate) within the validity period issued by the competent department of construction or its entrusted management organization, It is required not to be the project leader (Project Manager) of other construction projects under construction
.
3.2 consortium bidding is not accepted in this bidding
.
3.3 each bidder can bid for one of the above bid sections of this bidding project, but it is allowed to win at most one bid section (applicable to bidding projects with sub bid sections)
.
3.4 the bidder shall have the integrity archives Manual of Hainan construction enterprises
.
3.5 “credit China” website( www.creditchina.gov.cn )Inquiry: if the bidder is listed by the people’s court as the person to be executed for breach of trust, the bidding activities shall be restricted according to law
.
4
.
Acquisition of bidding documents 4.1 please visit the website of Haikou public resources trading website (ggzy
.
Haikou
.