Construction is not “closed” and may day power grid is busy

On May 3, when everyone took advantage of the small holiday to relax, the majority of power workers did not stop the pace of work

.

In Punan town of Zhangzhou City, the capacity increase project of No.1 main transformer of 220kV general substation is in full swing

.

During the holidays, the staff of the first four shifts of substation maintenance in the company’s Substation Maintenance Center enter the site in advance for process acceptance“ At present, the installation of No.1 main transformer body has been completed, and the main transformer vacuum pumping work is in progress

.

The purpose is to test the sealing of the main transformer, so as to carry out the subsequent hot oil circulation test

.

” Hong Wenbin, the person in charge of site acceptance, said

.

The capacity increase and reconstruction project of No.1 main transformer of Zongshan substation is an important reserve project for the company to meet the peak load in summer, which can effectively solve the problem of insufficient capacity of main transformer and provide additional assistance for high load operation of power grid in summer

.

The capacity of No.1 main transformer of Zongshan substation is increasing, and the transformer maintenance personnel are accepting the oil filter( Photo by Hong Wenbin) in Gulei Petrochemical Park of Zhangpu County, more than 100 kilometers away, the 220kV oil field substation is also in full swing

.

The 110kV GIS equipment Anti-corrosion facilities reconstruction project is under construction

.

At present, more than 20 staff members are engaged in the outdoor wall construction and painting of 110kV GIS switch room

.

The person in charge of the construction of Xinyuan engineering company on site said: “the oilfield substation is close to the seaside

.

In summer, the wind is strong and the salinity is high

.

It is easy to corrode the equipment

.

This anti-corrosion facility transformation work is to build an equipment building outside the 110kV GIS equipment area to resist the corrosion of the sea wind.” Speeding up the equipment transformation of oilfield transformer is an important measure for the company to promote the effective implementation of the “double satisfaction” project in the new era, and to implement the “big grasp of industry, big grasp of industry” and “top priority of Gulei” of Zhangzhou municipal Party committee and government

.

At the same time, on the construction site of Fujian Guangdong interconnection project in Mapu Township, Yunxiao County, there are also a group of power grid people busy: the project owner, the supervisor and the management personnel of the construction project department make reasonable arrangements for work scheduling, send personnel to the site all day long, and fully mobilize the equipment to carry out site clearing and slope stone replacement work from May 1 to 2, And work overtime to carry out site rolling test to ensure that the construction progress does not fall behind“ Today, due to the large-scale rainfall, according to the rainy season plan previously formulated, drainage is introduced to some ponding areas to reduce the impact of rainfall on Construction in time; At the same time, we will actively sort out the problems faced by the project and plan ahead of time to create good conditions for the subsequent smooth construction

.

” So says Zheng Zimo, a Fujian Guangdong Internet company

.

In order to ensure the stable operation of the power grid during the May Day holiday, the company optimized the operation mode of the power grid, scientifically scheduled the load forecasting, and carried out special power safety guidance for key users in advance; Transmission, transformation and distribution and other specialties carried out equipment special patrol maintenance and hidden danger investigation and treatment, and all emergency duty repair teams were ready to ensure that Zhangzhou was “bright” during the festival“ The spring breeze does not disappoint the passers-by, and the cause does not disappoint the strivers

.

” During the May Day holiday, the employees of the company stick to their posts and guard their responsibilities by ensuring power supply, construction and emergency duty, singing a song of labor belonging to the electric power man with their conscientious work( Lin Xin, Hong Wenbin, Zheng Zimo).

.