Construction report of civil engineering bid section 2 of Guiyang rail transit line 3 phase I Project Monday, May 3, 2021, weather: fine, temperature: 18 ~ 29 ℃ (1) output value completion (ten thousand yuan) 1
.
Per capita output value completed on plan day completion day weekly plan weekly completion proportion 72115.203.39500115.2023.04% monthly completion proportion in February plan year cumulative annual completion proportion 2000590.4029.52% 155003654.2023.58% 2 Construction progress completion project unit design quantity day plan day completion month plan month completion month completion proportion total completion Taohua right line ring 6285101554730% 358 Taohua left line ring 634561553523% 322 slag earthwork 6310050080015500410026% 34150 ① temporary construction of taohuazhai station: East track beam concrete pouring
.
The installation of pipeline protection template is completed
.
② The reinforcement construction of the south end shaft of taohuazhai station: 0 pilot holes, 594 pilot holes in total, 603 designed; 32 rotary jets were completed, 471 in total, 603 designed, 78% completed
.
3、 Construction management personnel and equipment input No
.
construction management personnel and equipment input note 1 tunneling team day shift: 50 persons night shift: 37 persons day shift: 4 persons night shift: 4 persons shield machine 2 gantry cranes 2 super capacitor locomotives 5 trains_ 2 earthwork team day shift: 5 people day shift: 1 excavator, 1 muck truck, 2 temporary construction teams day shift: 11 people day shift: 2 people day shift: 1 truck mounted crane
.
4
.
Safety production situation of working face at each working point of the project
.
Track beam concrete pouring at the east side of taohuazhai station
.
Segment assembly of left line in Taohua section
.
Segment assembly of right line in Taohua section
.
5、 Tomorrow’s construction plan project unit design quantity daily plan accumulated plan surplus Taohua right line ring 6285363265 Taohua left line ring 6345327307 muck outward transportation party 631005003465028450 south end shaft reinforcement of taohuazhai station: jet grouting pile grouting
.
Temporary construction of taohuazhai station: steel bar processing of starting guide platform, brick laying protection of up turning beam
.
6、 The reason analysis and action day plan for today’s plan has been completed
.
7、 Material mobilization: no new material
.
2
.
Equipment mobilization: no new equipment
.
8、 No memorabilia.
.