Windy weather, illegal lifting! Cloth machine falls in the air, the scene is breathtaking! Similar accidents: windy weather, lifting objects out of control, hit scaffolding! Life on the line! Windy weather, hanging basket does not stop working! Stop operation immediately in gale 6! Level 6 wind means level 6 wind on the tower crane
.
Sometimes there is not so much wind on the ground, but the wind on the tower crane is still very strong! Important reminder: in windy weather, it is illegal to command operations by force! According to the criminal law, a heavy sentence should be imposed! Don’t be paralyzed by luck and make fun of life! Construction safety management under gale weather 1
.
In case of gale weather above level 6, outdoor climbing and hanging work are not allowed
.
2
.
Temporary reinforcement measures against wind shall be taken for formwork during construction in strong wind
.
3
.
In case of gale of grade 6 or above, the erection and removal of scaffold shall be stopped, the removal and installation of outdoor formwork shall be suspended, and the open-air lifting operation shall be stopped
.
The construction elevator must stop running, lower the cage to the bottom and cut off the power supply
.
4
.
In case of strong wind of level 5 or above, all formwork lifting operations shall be stopped
.
5
.
In case of windy weather, the disassembly and assembly of tower crane shall be stopped
.
6
.
Tower crane lifting operation is not allowed when the wind force is level 4 or above
.
When the wind force suddenly increases to level 4 during the operation, it must be stopped immediately, and the connecting bolts of the upper and lower towers should be tightened
.
7
.
In case of gale of level 6 or above, it is strictly forbidden to install or dismantle the tower crane anchorage device
.
8
.
In case of Gale or gust of force 6 or above, the tower crane operation shall be stopped immediately, the rail clamp shall be locked, the brake of the slewing mechanism shall be released completely, and the boom shall be able to rotate with the wind
.
9
.
In case of gale of level 6 or above, the piling machine operation shall be stopped
.
When the wind exceeds level 7, the pile driver shall be stopped along the wind direction, and the cable wind rope shall be added, or the pile shall be laid down on the ground
.
10
.
The foundation pit and safety facilities shall be inspected in time after the strong wind with wind force of 6 or above
.
11
.
After the typhoon, the safety facilities for work at height shall be inspected one by one
.
If looseness, deformation, damage and falling off are found, they shall be repaired immediately
.
12
.
In case of strong wind and heavy rain, the scaffold and other foundation shall be inspected and accepted
.
13
.
The attached lifting scaffold shall not be lifted or dismantled in case of gale of grade 5 or above; When returning to work in case of gale of level 6 or above, it should be checked and confirmed to be qualified before use
.
14
.
When the construction of the hanging basket is in severe weather with a strong wind above level 5, the operation shall be stopped, the hanging basket platform shall be parked to the ground, and the steel wire rope and cable shall be bound and fixed
.
15
.
In case of gale above level 5, the tool scaffold shall not be lifted or lowered
.
16
.
The material hoist must stop running in the severe weather with the wind speed of 13m / s or above
.