Explanation and examples of filling in the “construction quality evaluation form of engineering project”

When filling in the construction quality evaluation form of engineering project, the following requirements must be met: 1

.

Project name: fill in according to the project name of the approved preliminary design report

.

2

.

Project grade: fill in the project grade, scale and main building grade

.

3

.

Construction site: fill in the specific place name of the hub project construction, such as province, county and township

.

4

.

Main quantities: fill in 2-3 items with the largest and second largest quantities

.

It must be filled in when there are main items such as concrete (including reinforced concrete), earthwork filling and masonry

.

5

.

Project legal person (construction unit): fill in the full name

.

6

.

The name of design, construction, supervision and other units shall fill in the full name used when signing the contract with the project legal person

.

If a project is undertaken by more than one construction (or design, supervision) unit, the full name of the unit undertaking the main task only needs to be filled in the table, and the full name of all the units undertaking the task and the name of the unit project completed by each unit are listed in the attached page

.

If the project is completed by one contractor and several subcontractors, only the full name of the Contractor shall be filled in the table, and the full name of the subcontractor and the completed project name shall be listed in the attached sheet

.

7

.

Commencement date: fill in the year (4 digits) and month when the main project starts

.

Completion date: fill in the year (4 digits) and month when all the contents specified in the approved design are completed

.

8

.

Evaluation date: fill in the actual date of project quality grade evaluation

.

9

.

Main building unit works: main buildings refer to the buildings that will cause downstream disasters or seriously affect the project benefits after the accident, such as dams, discharge structures, water conveyance structures, power plants and pumping stations

.

10

.

This form shall be filled in by the project director after the contents specified in the approved design of the project have been completed and the construction quality grade of each unit project has been assessed, and the project quality shall be assessed

.

The person in charge of the supervision unit shall sign and affix the official seal

.

If the project is supervised by multiple supervision units, the, The project director of each supervision unit is responsible for the statistics of the unit project quality evaluation results (including the quality statistics of unit project and divisional project) and the statistics of main quantities supervised by the unit, and submit them to the project legal person

.

Then the project director of a main supervision unit is entrusted by the project legal person to collect the statistical data of each unit, fill in the project quality evaluation form, sign and affix the official seal of the supervision unit

.

It shall be submitted to the project legal person for evaluation, signed and sealed by the legal representative of the project legal person, and submitted to the quality supervision organization for approval

.

11

.

Construction quality evaluation standard of engineering project: the quality of unit project is all qualified; During the construction period and trial operation period of the project, the analysis results of the observation data of each unit project meet the requirements of the national and industrial technical standards and the standards agreed in the contract

.

Excellent standard: the quality of all unit projects is qualified, of which more than 70% are excellent, and the quality of main unit projects is excellent; During the construction period and trial operation period of the project, the analysis results of the observation data of each unit project meet the requirements of the national and industrial technical standards and the standards agreed in the contract

.