Full set of construction technology disclosure summary! Suggest collection!

Source: the copyright of the network belongs to the original owner 01 the role and classification of technical disclosure 1 what is the construction technical disclosure? Technical disclosure is a very important technical management work of construction enterprises, is the continuation and improvement of the construction scheme, and is also the last pass of project quality pre control

.

The purpose is to make the technical personnel and workers involved in the construction familiar with and understand the characteristics, design intent, technical requirements, construction technology and problems that should be paid attention to

.

2

.

The role of technical disclosure enables every technical personnel participating in the construction activities to make clear the specific construction conditions, construction organization, specific technical requirements and targeted key technical measures of the project, and systematically grasp the overall picture of the construction process and the key position of the construction

.

  Through the technical disclosure, each worker participating in the construction operation of the project can understand the specific work content, operation method, construction technology, quality standard and safety precautions of the divisional and sub divisional works to be completed, so as to make the task of the construction operators clear and have a clear idea, and achieve the purpose of orderly construction, so as to reduce various common quality problems and improve the construction quality

.

3 Classification of construction technology disclosure (1) construction organization design disclosure (1) key and large-scale project construction organization design disclosure: the technical director of the construction enterprise shall disclose the main design requirements, construction measures and important matters to the main project management personnel

.

Other engineering construction organization design disclosure shall be conducted by the project technical director

.

② Technical disclosure of special construction scheme: the professional technical director of the project is responsible for the disclosure to the professional foreman according to the special construction scheme( 2) The construction technical disclosure of sub project shall be conducted by the professional foreman to the professional construction team (or professional subcontracting)“ “Four new” technical disclosure: the technical director of the project shall organize relevant professional personnel to prepare and disclose( 3) Technical disclosure of design change technical disclosure of design change: the technical department of the project shall disclose to the professional foreman according to the change requirements and in combination with the specific construction steps, measures and precautions( 4) The special disclosure of surveying engineering shall be made by the engineering and technical personnel to the surveyors( 5) Safety technical disclosure the technical personnel in charge of project management shall disclose the technical requirements for safe construction to the construction teams and operators

.

02 compilation requirements of construction technical disclosure 1

.

It must comply with the construction specifications, technical operation procedures, quality acceptance specifications, engineering quality evaluation standards and other corresponding provisions

.

2

.

It is necessary to implement various national technical standards, including units of measurement and names

.

3

.

Meet and realize the technical requirements in the design and construction drawings

.

4

.

5

.

For different levels of construction personnel, the depth and detail of technical disclosure are different, That is to say, the depth of the content and the way of explanation for different personnel should be targeted

.

6

.

Technical disclosure should strive to achieve: the main items are complete, the contents are specific and clear, conform to the specifications, the key points are prominent, the expressions are accurate, the values are based, and the diagrams are supplemented when necessary

.

It can play a guiding role in engineering construction, with pertinence, guidance and operability

.

7

.

There should be no reference for “matters not covered” in technical disclosure ×××××( And so on

.

  The construction technical disclosure shall be organized by the technical director of the project, and specifically prepared by the professional foreman and / or the professional technical director

.

After being approved by the technical director of the project, the professional foreman and / or the professional technical director shall make the disclosure to the construction team leader and all construction workers

.

8

.

The construction technical disclosure shall be conducted before the project construction

.

03 compilation content of technical disclosure 1 compilation format of technical disclosure (1) project overview (2) work content and workload (3) quality, safety, progress, civilized construction, environmental protection and other objectives (4) construction preparation (1) material preparation; ② Equipment preparation; ③ Working conditions and personnel preparation( 5) Operation process: 1; ② Operation preparation; ③ Construction technology( 6) Quality standard: 1; ② General items; ③ Quality control points( 7) Finished product protection (8) safety and environment (9) construction precautions 2 contents of construction technical disclosure (1) the contents of technical disclosure conducted by the chief engineer of the construction unit to the project manager and technical director of the project shall include the following main aspects: (1) project overview and various technical and economic indicators and requirements; ② Main construction methods, key construction technologies and problems in implementation; ③ Technical treatment details and precautions of special engineering parts; ④ New technology, new technology, new materials, new structure construction technical requirements and implementation plan and matters needing attention; ⑤ Construction organization design network plan, schedule requirements, construction deployment, construction machinery, labor arrangement and organization; ⑥ The cooperation between the general contractor and the subcontractor and the handling of related problems; ⑦ Construction quality standard and safety technology; ⑧ Try to adopt the standardized operation such as the construction method carried out by the unit( 2) The technical disclosure of the project technical director to the unit project director, quality inspector and safety officer includes the following aspects: (1) engineering situation and local topography, landform, engineering geology and various technical and economic indicators; ② The specific requirements, methods and construction difficulties of design paper; ③ Specific requirements and implementation steps and methods of construction organization design or construction scheme; ④ The specific methods of construction, the process standards and the construction methods of the enterprise; Key parts and possible problems and solutions in the implementation process; ⑤ Construction schedule requirements, procedure overlapping, construction deployment and construction team task determination; ⑥ The type, quantity, entering time and operation procedure of main construction machinery used in construction; ⑦ Relevant operation procedures, technical regulations and matters needing attention of new technology, new structure and new materials; ⑧ Construction quality standards and safety technology specific measures and precautions( 3) The contents of technical disclosure made by the professional foreman to the team leaders and workers of various types of work are as follows: 1

.

Focus on the specific technical requirements of the divisional and subdivisional works that each operation team is responsible for, and the construction process standards or internal construction methods adopted; ② Construction quality standards for divisional and subdivisional works; ③ Preventive measures and precautions for common quality problems; ④ The construction safety disclosure and the safety accident lessons of previous similar projects and the specific safety countermeasures should be taken are introduced

.

04 technical disclosure key 1 earthwork (1) properties and characteristics of foundation soil( 2) The location and protection methods of various stakes( 3) The scope and depth of excavation and filling, the requirements of side slope, the compaction method of backfill and lime soil, and the index requirements of unit weight, etc( 4) Groundwater or surface water drainage and treatment methods( 5) Relevant regulations and safety technical measures of construction technology and operation procedures

.

2 masonry works (1) masonry parts( 2) Axis position( 3) Horizontal elevation of each floor( 4) Location of door and window openings( 5) Wall thickness and wall thickness changes( 6) Mortar strength grade, mortar mix proportion, number of mortar test blocks and maintenance( 7) Location, quantity, specification and size of each reserved hole and embedded parts of each specialty( 8) Quality requirements of raw materials such as bricks and stones at different positions and elevations( 9) Methods and quality standards of masonry construction( 10) Prevention measures of common quality problems, safety precautions, etc.

.