New friends click above Blue words When paying attention to the construction site, it is necessary to identify, evaluate and update the major hazard sources in time
.
During the safety inspection of the construction site, it is necessary to focus on monitoring the major hazard sources
.
1
.
Floor type scaffold Inspection points of construction scheme Whether the scaffold has a construction plan; Whether the scaffold height exceeds the specification; No design calculation or approval; Whether the construction scheme can guide the construction
.
★ Inspection points of vertical pole foundation Whether the pole foundation is flat and solid every 10 meters, which meets the design requirements; Whether there is a lack of base and skid for every 10 meters of extension pole; Whether there is a sweeping pole for every 10 meters of extension pole; Whether there are drainage measures every 10 meters
.
★ Key points for checking the tie between frame and building structure If the height of scaffold is more than 7 meters, whether the scaffold is tied with the building structure, and whether it is lack or not firmly tied according to the requirements
.
★ Inspection points of component spacing and cross bracing Whether the distance between the vertical bar, large cross bar and small cross bar exceeds the specified requirements every 10 meters; Whether the cross bracing is set according to the regulations; Whether the cross bracing is set continuously along the scaffold height and whether the angle meets the requirements
.
★ Inspection points of scaffold and protective railing Whether the scaffold board is fully paved; Whether the scaffold board material meets the requirements; Whether there is a probe board; Whether the dense mesh safety net is set outside the scaffold and whether the net is tight; Whether the construction layer is provided with 1.2m high protective railings and toe boards
.
★ Inspection points of small cross bar setting Whether a small cross bar is set at the intersection of the vertical bar and the large cross bar; Whether the small cross bar is fixed at one end only; Whether the cross bar of single row shelf inserted into the wall is less than 24cm
.
★ Inspection points of disclosure and acceptance Whether there is disclosure before scaffold erection; Whether the acceptance procedures are handled after the scaffold is erected; Whether there is quantitative acceptance content
.
★ Key points for inspection of rod lapping Whether the overlap of large cross bar is less than 1.5m; Whether the steel pipe poles are overlapped, and whether the overlapping length of cross bracing meets the requirements
.
★ Key points for inspection of frame sealing Whether flat net or other measures are used to close the construction layer every 10 meters; Whether the vertical pole in the scaffold of the construction layer is closed with the building
.
★ Inspection points of scaffold materials Whether the steel pipe is seriously bent or corroded
.
★ Inspection points of safe passage Whether the frame is equipped with upper and lower channels; Whether the channel settings meet the requirements
.
★ Inspection points of unloading platform Whether the unloading platform has been designed and calculated; Whether the unloading platform meets the design requirements; Whether the support system of the unloading platform is connected with the scaffold; Whether the unloading platform has a limited load label
.
2
.
Cantilever scaffold Inspection points of construction scheme Whether the scaffold has a construction plan; Whether the design document has been approved by the superior; Whether the erection method in the scheme is specific
.
★ Inspection points of cantilever beam and frame stability Whether the overhanging member is firmly tied with the building; Whether the cantilever beam installation meets the requirements; Whether the bottom of the vertical pole is fixed firmly; Whether the frame is tied to the building as required
.
★ Inspection points of scaffold board Whether the scaffold board is laid tightly and firmly; Whether the scaffold board material meets the requirements; Whether there is a probe
.
★ Key points of load inspection Whether the load of scaffold board exceeds the requirements; Whether the construction load is stacked evenly
.
★ Inspection points of disclosure and acceptance Whether the scaffold erection meets the requirements; Whether the erection of each section of scaffold is accepted; Whether there is disclosure
.
★ Key points for inspection of bar spacing Whether the pole per 10 meters of extension exceeds the requirements; The distance between large cross bars exceeds the specification
.
★ Inspection points of frame protection Whether 1.2m high protective railings and toe boards are set outside the construction layer; Whether the dense mesh safety net is set outside the scaffold and whether the net is tight
.
★ Inspection points of interlayer protection Whether there is horizontal net or other protection measures under the operation layer; Whether the protection is tight
.
★ Inspection points of scaffold materials Whether the specification and material of bar, fastener and section steel meet the requirements
.
3
.
Portal scaffold Inspection points of construction scheme Whether the scaffold has a construction plan; Whether the construction scheme meets the specification requirements; Whether the scaffold is designed or approved by the superior
.
★ Inspection points of frame foundation Whether the scaffold foundation is smooth; Whether there is a sweeping pole at the bottom of the scaffold
.
★ Key points of frame stability inspection Whether it is tied to the wall as required; Whether the tie is firm; Whether the cross bracing is set according to the regulations; Whether the deviation of gantry vertical pole exceeds the specification
.
★ Key points for inspection of bar lock Whether it is assembled according to the instructions; Whether the assembly is firm
.
★ Inspection points of scaffold board Whether the scaffold board is fully paved and the distance from the wall is more than 10cm; Whether the scaffold board material meets the requirements
.
★ Inspection points of disclosure and acceptance Whether there is disclosure for scaffold erection; Whether the erection of each section of scaffold is accepted
.
★ Inspection points of frame protection Whether 1.2m guard rail and 18cm toe board are set outside the scaffold; Whether the dense mesh is hung outside the frame and whether the mesh is tight
.
★ Inspection points of bar material Whether the member is deformed or not; Whether there is local welding; Whether the rod is rusted and not painted
.
★ Key points of load inspection Whether the construction load exceeds the requirements; Whether the scaffold load is stacked evenly
.
★ Key points of channel inspection Whether the upper and lower channels are set; Whether the channel settings meet the requirements
.
4
.
Scaffolding Inspection points of construction scheme Whether the scaffold has a construction plan; Whether the construction scheme meets the specification requirements; Whether the construction scheme is instructive
.
★ Inspection points of production and assembly Whether the fabrication and assembly of the frame meet the design requirements; Whether the suspension point is designed and whether the design is reasonable; Whether the fabrication and embedding of suspension point components meet the design requirements; Whether the distance between suspension points is more than 2m
.
★ Inspection points of bar material Whether the material meets the design requirements, whether the bar deformation is serious, and whether the local welding is open; Whether the rod and parts are rusted and painted with protective paint
.
★ Inspection points of scaffold Whether the scaffold is fully paved and firm; Whether the scaffold board material meets the requirements; Whether there is a probe
.
★ Inspection points of disclosure acceptance Whether the scaffold enters the site for acceptance; Load test before the first use; Check whether the acceptance data are comprehensive before each use
.
★ Key points of load inspection Whether the construction load exceeds 1kn; Whether there are more than 2 people working on each span
.
★ Inspection points of frame protection Whether 1.2m high protective railings and toe boards are set outside the construction layer; Whether the dense mesh safety net is set outside the scaffold and whether the net is tight; Whether the bottom of scaffold is closed tightly
.
★ Inspection points of installation personnel Whether the scaffold installation personnel have received professional training; Whether the installation personnel wear the safety belt
.
5
.
Basket scaffold Inspection points of construction scheme Whether there is a construction plan; The construction has design calculation sheet or has not been approved; Whether the construction plan guides the construction
.
★ Inspection points of production and assembly Whether the cantilever anchorage or counterweight is qualified for anti overturning; Whether the basket assembly meets the requirements; Whether the electric hoist is a qualified product; Whether the hanging basket has been load tested before use
.
★ Inspection points of safety devices Whether the hoist has a warranty card and whether it is valid; Whether the lifting basket has a safety rope and whether it is effective; Whether there is hook insurance; Whether the operators fasten the safety belt and whether the safety belt is hung on the lifting rope of the hanging basket
.
★ Inspection points of scaffold board Whether the scaffold board is fully paved; Whether the scaffold board material meets the requirements; Whether there is a probe.
.