【1】 Construction organization design of specialized college-2333 unit project

1

.

The application and promotion of the overall planning method in the construction industry started from ()

.

A

.

Before the completion of the project, the site around the building is clean and tidy, and the distance is within ()

.

A

.

2 meters, B.3 meters, C.4 meters, d.5 meters answer: Click to check the answer 3

.

The correct relationship between the number of construction sections m and the number of construction process n of flow construction is ()

.

A

.

M < n, B.M ≤ n, C.M = n, D.M ≥ n answer: Click to check the answer

.

4

.

When compiling the construction plan of unit project, first determine the () position

.

A

.

Warehouse, B

.

lifting equipment, C

.

office building, D

.

Road

.

A

.

Construction project, B

.

divisional project, C

.

unit project, D

.

subdivisional project

.

A

.

Transportation, B

.

water supply and power supply conditions, C

.

local resources, D

.

topographic data answer: Click to view the answer 7

.

Which of the following is the content of the engineering technical and economic conditions investigation(    ) A

.

Traffic and transportation, B

.

engineering hydrogeology, C

.

topographic map, D

.

meteorological data

.

A

.

Long cycle, B

.

fixity, C

.

diversity, D

.

bulky answer: Click to view the answer 9

.

The main advantages of network diagram are () A

.

simple preparation, B

.

intuitive and easy to understand, C

.

convenient calculation, D

.

clear logical relationship of process answer: Click to view the answer 10

.

Virtual work in double code network diagram()

.

A

.

It does not take up time but consumes resources

.

B

.

It does not take up time and consumes resources

.

C

.

It takes up time and consumes resources

.

D

.

It takes up time and consumes resources

.

Answer: Click to view the answer

.

11

.

In the double code network diagram, the start or end time of an operation should be noted in ()

.

A

.

Above the arrow shaft, B

.

in the circle, C

.

below the arrow shaft, D

.

above and below the arrow shaft

.

A

.

Topographic map, B

.

engineering hydrogeology, C

.

transportation, D

.

meteorological data answer: Click to view the answer 13

.

The lime warehouse and ash shower pool should be arranged close to the mortar mixing station and arranged in the construction site

.

A

.

Up wind direction, B

.

down wind direction, C

.

close to the yard, D

.

unlimited position

.

Answer: Click to check the answer 14

.

The () method can achieve continuous, balanced and rhythmic organization of construction

.

A

.

parallel construction, B

.

sequential construction, C

.

flow construction, D

.

phased construction answer: Click to check the answer 15

.

The basic principle adopted in the formulation of construction engineering quota in China is ()

.

A

.

The biggest difference between the double code network diagram and the single code network diagram is () A

.

different node numbers, B

.

different symbols for work, C

.

different application scopes, D

.

different parameter calculation methods

.

Answer: Click to view the answer 17

.

The production process of building products has a wide range of contacts, Strong comprehensiveness is due to the development of construction products

.

A

.

Fixed, B

.

diversity, C

.

bulky, D

.

long production cycle(  )。 A

.

The most scientific construction schedule is () A

.

bar chart, B

.

oblique line chart, C

.

broken line chart, D

.

network chart answer: Click to view the answer 20

.

The flow construction scheme of outdoor decoration engineering generally adopts ()

.

A

.

Top down, B

.

bottom up, C

.

left to right, D

.

right to left answers: Click to see the answers.

.