1
.
The application and promotion of the overall planning method in the construction industry started from ()
.
A
.
Before the completion of the project, the site around the building is clean and tidy, and the distance is within ()
.
A
.
2 meters, B.3 meters, C.4 meters, d.5 meters answer: Click to check the answer 3
.
The correct relationship between the number of construction sections m and the number of construction process n of flow construction is ()
.
A
.
M < n, B.M ≤ n, C.M = n, D.M ≥ n answer: Click to check the answer
.
4
.
When compiling the construction plan of unit project, first determine the () position
.
A
.
Warehouse, B
.
lifting equipment, C
.
office building, D
.
Road
.
A
.
Construction project, B
.
divisional project, C
.
unit project, D
.
subdivisional project
.
A
.
Transportation, B
.
water supply and power supply conditions, C
.
local resources, D
.
topographic data answer: Click to view the answer 7
.
Which of the following is the content of the engineering technical and economic conditions investigation( ) A
.
Traffic and transportation, B
.
engineering hydrogeology, C
.
topographic map, D
.
meteorological data
.
A
.
Long cycle, B
.
fixity, C
.
diversity, D
.
bulky answer: Click to view the answer 9
.
The main advantages of network diagram are () A
.
simple preparation, B
.
intuitive and easy to understand, C
.
convenient calculation, D
.
clear logical relationship of process answer: Click to view the answer 10
.
Virtual work in double code network diagram()
.
A
.
It does not take up time but consumes resources
.
B
.
It does not take up time and consumes resources
.
C
.
It takes up time and consumes resources
.
D
.
It takes up time and consumes resources
.
Answer: Click to view the answer
.
11
.
In the double code network diagram, the start or end time of an operation should be noted in ()
.
A
.
Above the arrow shaft, B
.
in the circle, C
.
below the arrow shaft, D
.
above and below the arrow shaft
.
A
.
Topographic map, B
.
engineering hydrogeology, C
.
transportation, D
.
meteorological data answer: Click to view the answer 13
.
The lime warehouse and ash shower pool should be arranged close to the mortar mixing station and arranged in the construction site
.
A
.
Up wind direction, B
.
down wind direction, C
.
close to the yard, D
.
unlimited position
.
Answer: Click to check the answer 14
.
The () method can achieve continuous, balanced and rhythmic organization of construction
.
A
.
parallel construction, B
.
sequential construction, C
.
flow construction, D
.
phased construction answer: Click to check the answer 15
.
The basic principle adopted in the formulation of construction engineering quota in China is ()
.
A
.
The biggest difference between the double code network diagram and the single code network diagram is () A
.
different node numbers, B
.
different symbols for work, C
.
different application scopes, D
.
different parameter calculation methods
.
Answer: Click to view the answer 17
.
The production process of building products has a wide range of contacts, Strong comprehensiveness is due to the development of construction products
.
A
.
Fixed, B
.
diversity, C
.
bulky, D
.
long production cycle( )。 A
.
The most scientific construction schedule is () A
.
bar chart, B
.
oblique line chart, C
.
broken line chart, D
.
network chart answer: Click to view the answer 20
.
The flow construction scheme of outdoor decoration engineering generally adopts ()
.
A
.
Top down, B
.
bottom up, C
.
left to right, D
.
right to left answers: Click to see the answers.
.