1

.

The flow parameters of the working duration of the working team (Group) engaged in a certain construction process in a construction section are ()

.

A

.

The advantages of using network diagram to express plan content in construction engineering are as follows

.

A

.

Process relationship is clear, B

.

can focus on management, C

.

simple preparation, D

.

can optimize, e

.

can calculate by computer

.

A

.

Construction organization design can be divided into () A

.

general design of construction organization, B

.

construction organization design of unit project, C

.

construction organization design of divisional and subdivisional project

.

Answer: Click to view the answer

.

The characteristics of single code network diagram are () A

.

node represents work, B

.

virtual process, C

.

The construction features of multi-storey mixed structure civil buildings are as follows: (1) large amount of earthwork, B

.

large amount of decoration, C

.

large amount of prefabrication, D

.

large amount of bricklaying, E

.

Easy to organize flow construction answer: Click to view the answer 7

.

The quantitative analysis index of construction scheme mainly includes ()

.

A

.

Construction period index, B

.

mechanization degree, C

.

cost reduction index, D

.

main material saving index, e

.

labor consumption index per unit building area answer: Click to check the answer 8

.

The basis for determining the construction sequence of the project is ()

.

A

.

Construction period, B

.

quality, C

.

structural features, D

.

resource supply, e

.

construction cost answer: Click to view the answer 9

.

Flow parameters include ()

.

A

.

Process parameters, B

.

time parameters, C

.

space parameters, D

.

parallel parameters answer: Click to view the answer 10

.

Space parameters of flow construction include ()

.

A

.

Working face, B

.

flow distance, C

.

flow rhythm, D

.

construction section, e

.

construction layer answer: Click to check the answer 11

.

Flow construction process parameters mainly include () A

.

construction process, B

.

construction section, C

.

flow intensity, D

.

construction layer, e

.

flow distance answer: Click to check the answer 12

.

Organization construction should pay attention to () link

.

A

.

Investment, B

.

plan, C

.

design, D

.

construction, e

.

investigation answer: Click to view the answer 13

.

The main work of the investment decision-making stage of construction project is () A

.

feasibility study, B

.

estimation and project approval, C

.

design preparation, D

.

selection of construction site, e

.

economic analysis answer: Click to view the answer 14

.

The basis of construction plan design mainly includes () A

.

local natural conditions, B

.

technical and economic conditions, C

.

Design information, D

.

main construction scheme, e

.

construction schedule answer: Click to view the answer 15

.

Main content of unit construction organization design (), etc

.

A

.

Project overview, B

.

construction plan, C

.

construction progress, D

.

construction plan, e

.

construction preparation plan answer: Click to view the answer 16

.

The “three calculation” of construction engineering is ()

.

A

.

Design budget, B

.

construction drawing budget, C

.

construction budget, D

.

completion settlement, e

.

completion settlement answer: Click to view the answer 17

.

Construction procedures generally include () these stages

.

A

.

Determine the construction task, B

.

construction planning, C

.

construction preparation, D

.

organization of construction, e

.

completion acceptance answer: Click to view the answer 18

.

The most basic quota of construction engineering quota is ()

.

A

.

Labor quota, B

.

budget quota, C

.

time quota, D

.

material consumption quota, e

.

usage quota of machine shift

.

A

.

The work structure is clear, B

.

the logical relationship is correct, C

.

the time calculation is accurate, D

.

the compilation is in line with the regulations

.

A

.

First on the ground and then underground, B

.

first underground and then on the ground, C

.

first deep and then shallow, D

.

first shallow and then deep, e

.

first main body and then decoration.

.