The construction content and scale of Chengpeng viaduct into the city: the total length is about 3128m, and the width of red line is 40m
.
The construction content includes road, bridge, up and down ramp, pipeline relocation, traffic safety (including intelligent transportation), greening landscape and other municipal supporting facilities
.
Construction site: the project is located in rongbei business Avenue, starting from saiyuntai road and ending at Zhonghuan road
.
With the expansion and reconstruction of the north railway station and the demolition of Wukuaishi, some people asked about the demolition of this area and the construction of the broken business avenue for many years
.
In recent months, there has been no work stoppage
.
When will the construction be completed and it will be more convenient to drive? According to the investigation of Wukuaishi sub district office in Jinniu District, No.1 courtyard of zhanxiqiaodong lane is an old courtyard
.
The courtyard was built in the 1990s
.
The houses are old, and the supporting facilities of the surrounding public buildings are not perfect
.
Some people have strong desire for transformation
.
In recent years, they have repeatedly reflected their transformation demands in the streets and communities
.
In order to better grasp the wishes of the masses, saiyuntai community carried out a survey on the residents’ intention to transform the courtyard in 2020
.
The street has reflected the intention investigation to the relevant departments, and according to the work arrangement, there is no reconstruction plan for the courtyard
.
According to the information in December 2020, the main bridge of Shangmao Avenue is basically completed except for the land acquisition and demolition of the bridge section
.
In view of the delay in demolition, Jinniu District has been actively cooperated to carry out land acquisition and demolition for many times; As of December last year, the household contract has been basically completed
.
Jinniu District completed the demolition and land delivery in March 2021
.
After the completion of the demolition and land delivery, our company immediately organized the construction personnel to enter the site for construction
.
It is expected that the main bridge of Shangmao Avenue will be connected in September 2021
.
The current schedule of Chengpeng viaduct into the city section is Commercial Avenue, which is the construction scope of Chengpeng viaduct into the city section under the construction management of construction group
.
The project will enter the construction site at the end of March 2019; Due to the influence of many factors, such as land removal and handover, pipeline relocation, Metro site handover, safety assessment, relevant requirements of Railway Administration, epidemic situation and so on, the project progress lags behind
.
According to the current project construction progress and schedule, it is expected to be fully completed by the end of September 2021
.
Source: Leshan village, Chengdu 👇 click
.