01 due to the renovation of the front door of Shanxi workers’ newspaper (No
.
8, Xinmin middle street), it will occupy the position in front of the door from 0:00 on May 8 to 24:00 on May 31, 2021
.
Pedestrians and vehicles are requested to avoid and pass safely
.
02 due to the construction needs of Taiyuan customs (No
.
112 Xuefu Street) to build a parking building, it will occupy the southwest corner of Changzhi Road and Xuefu street for enclosure construction from May 8 to June 30, 2021
.
At that time, a safe pedestrian passage will be built
.
Please pay attention to the safety of pedestrians and vehicles
.
03 due to the construction needs of Taiyuan wangjiafeng 110kV power transmission and transformation project, from May 8 to June 30, 2021, pumping and desilting and cable laying will be carried out on Jianshe South Road (South Shifang Street Qinxian North Street), Qinxian North Street (Jianshe South Road TIYU Road) and TIYU Road (Qinxian North Street Yongkang Street)
.
Pedestrians and vehicles are requested to avoid the operation site and pass safely..
.