Click on “Xi’an public security” above to subscribe to the notice of Traffic Management Bureau of Xi’an Public Security Bureau on strengthening traffic management of Weiling Street (electronic West Street Yannan 2nd Road) Municipal Engineering EPC project by closing the construction of electronic 4th Road and Mingde 2nd road, Xi’an Weiling Street (electronic West Street to Yannan 2nd Road) Municipal Engineering (phase I) EPC project construction, the near future will be the electronic 4th Road, Mingde 2nd Road part of the road for closed construction
.
The specific closed road sections are as follows: the construction will carry out the full closed enclosure construction for the fourth electronic road (190m to the west of the intersection of the main electronic street) and the second Mingde Road (Dongyi road to Hanguang road and Hanguang road to the front of Mingde middle school)
.
The closure time is as follows: the construction of the enclosure of the fourth electronic road (190m to the west of the intersection of the main electronic street) will start at 23:00 on April 27, 2021, and end at 23:00 on May 27, 2021, with a construction period of 30 days; The enclosure construction of Mingde Second Road (Dongyi road to Hanguang Road, Hanguang road to the front of Mingde middle school) will start at 23:00 on April 27, 2021 and end at 23:00 on June 11, 2021
.
The construction period is planned to be 45 days
.
The traffic police department said that during the construction period, all vehicles, non motor vehicles and some pedestrians were prohibited to pass on dianzi 4th Road (190m west of the intersection of dianzi Main Street) and Mingde 2nd Road (Dongyi road to Hanguang road and Hanguang road to the front of Mingde middle school), 1
.
Pedestrian detour route: reserve a 2-meter-wide sidewalk on the south side of the enclosure or detour to e-san road via E-main street and e-west street
.
2
.
Non motor vehicle detour route: detour through electronic main street and electronic West Street to electronic third road
.
3
.
Detour route for motor vehicles: from west to East, vehicles pass through electronic West Street and bypass electronic second road and Zhangba East Road; From the east to the west, the vehicles will pass through the electronic main street and bypass the electronic second road and Zhangba East Road( 2) Mingde 2nd Road (Dongyi road to Hanguang Road, Hanguang road to front of Mingde middle school) 1
.
Detour routes for pedestrians and non motor vehicles: pass through Dongyi Road, Mingde 1st road to the south section of Hanguang road or Mingde Road (in front of Mingde middle school)
.
2
.
Detour route for motor vehicles: from west to East, vehicles can pass through Dongyi Road, detour Electronic Road 2, Mingde Road 1, Mingde Road West and Zhangba Road East; From east to west, vehicles can pass through Mingde road and bypass Electronic Road 2, Mingde Road 1, Mingde Road West and Zhangba Road East; From the north to the south, vehicles pass through electronic road 2 to Dongyi Road, Mingde road and Zhuque street
.
At the same time, Xiaobu learned that these road sections will be closed and fenced
.
During the construction period, the road will become narrower and the traffic capacity will drop significantly
.
Xi’an Public Security Bureau Traffic Management Bureau’s notice on strengthening traffic management in the main construction of kaiyuanmen station phase I of Metro Line 8
.
The main construction of kaiyuanmen station phase I of Metro Line 8 will be implemented in the near future, According to the relevant provisions of the road traffic safety law of the people’s Republic of China and the regulations for the implementation of the road traffic safety law of the people’s Republic of China, combined with the construction demand and traffic conditions, the traffic management work during the construction period of Xi’an Public Security Bureau is hereby announced as follows: the construction time of the project is from 23:00 on April 26, 2021, and the planned construction period is 12 months
.
The specific construction section is: to the north of Daqing Road Fenghui road cross, part of the motorway is enclosed from south to north
.
The enclosure is about 305 meters long and 10.2 meters wide
.
During the construction period, two 3-meter motorways are set under the viaduct of West 2nd Ring Road on the west side of the enclosure for vehicles from south to north, and one 3.3-meter bus lane and one 2.5-meter non motorway are set on the east side of the enclosure for buses and non motor vehicles from south to north; The original three motorways, non motorways and sidewalks of Fenghui route from north to South remain unchanged
.
During the construction period, the road becomes narrower and the traffic capacity decreases obviously
.
It is forbidden to park in the construction section and the surrounding area; Please pay attention to the traffic safety of passing vehicles and pedestrians, follow the traffic signs and markings, or choose a detour in advance
.
Notice of Xi’an Public Security Bureau Traffic Management Bureau on strengthening traffic management in main construction of Tumen station phase II of Metro Line 8, According to the relevant provisions of the road traffic safety law of the people’s Republic of China and the regulations for the implementation of the road traffic safety law of the people’s Republic of China, combined with the construction demand and traffic conditions, the traffic management work during the construction period of Xi’an Public Security Bureau is hereby announced as follows: the construction time of the project is from 23:00 on April 26, 2021, and the planned construction period is 12 months
.
The specific construction section is: Fenghui road FengHao Road intersection from north to south, part of the motorway is enclosed, divided into two parts
.
The first fence is located in the north of Fenghui road FengHao Road intersection, with a length of 96 meters and a width of 13.8 meters; The second fence is located in the south of Fenghui road FengHao Road intersection
.
The fence is about 88 meters long and 32.1 meters wide
.
During the construction period, Fenghui route is in the north-south direction, and three 3M straight motorways are set on the east side of the first enclosure; A 3-meter right turn motorway is set on the west side of the enclosure for right turn vehicles from north to west; The bus lane, non motorized lane and sidewalk of 3.3m from north to South remain unchanged; Three 3 m straight motor vehicle lanes are set in the east of the second enclosure, and one 3.3 m motor vehicle lane is set in the west of the enclosure for north to South motor vehicles, while the non motor vehicle lane and sidewalk remain unchanged
.
The original traffic mode of Fenghui route in the south to north direction remains unchanged
.
FengHao road is East-West two-way, with 6 motorways in the middle of the first and second enclosure
.
From east to west, three motorways (two 3M wide and one 3.3m wide), one 2.5m non motorized vehicle and one 2m sidewalk are set; From west to East, three motorways (two 3M wide and one 3.3m wide), one 2.5m non motorized vehicle and one 2m sidewalk are set; Guardrails are used to separate the motorway from the non motorway; FengHao west road turns right from west to south, and vehicles pass through the 3.3m motorway reserved on the west side of the second enclosure
.
During the construction period, the road becomes narrower and the traffic capacity decreases obviously
.
It is forbidden to park in the construction section and the surrounding area; Please pay attention to the traffic safety of passing vehicles and pedestrians, follow the traffic signs and markings, or choose a detour in advance
.
Notice of traffic administration bureau of Xi’an Public Security Bureau on strengthening traffic management in main construction of hongmiaopo station of Metro Line 8 the construction of main construction of hongmiaopo station of Metro Line 8 in Xi’an will be implemented in the near future
.
Traffic Administration Bureau of Xi’an Public Security Bureau, in accordance with relevant provisions of road traffic safety law of the people’s Republic of China and regulations on implementation of road traffic safety law of the people’s Republic of China, Combined with the construction demand and traffic conditions, the traffic management work during the construction period is announced as follows: the construction time of the project is from 23:00 on April 26, 2021, and the planned construction period is 12 months
.
The specific construction section is: part of the motorway in the southeast of Xinghuo road Liyuan Road Cross is enclosed
.
The enclosure is about 332.9m long and 38m wide.
.