3000 workers keep working! Another key project in Wanzhou is under rapid construction! The location is

In June, the investment reached 3.48 billion yuan, a new high since 2018

.

According to Yuan Zuming, manager of Project Department of bid section II of phase I of Wanzhou Comprehensive Bonded Zone, “bid section II of phase I of Wanzhou comprehensive bonded zone includes office area, checkpoint, inspection area, inspection and quarantine area, fence, informatization and other construction contents

.

All responsible departments and units strengthen cooperation, form a joint force, pay close attention to the preliminary work such as design and approval, strengthen the guarantee of land, capital and other elements, strictly control the quality and safety of the project, and strive to complete the project as soon as possible Early results

.

2

.

” On the construction site, nearly 3000 builders kept working

.

We strive to complete the completion acceptance in October, Ensure the closing and operation at the end of the year

.

Grasping projects is grasping development

.

The whole region has established a project promotion mechanism

.

1 boiler in the thermoelectric process has been completed by 70%, and the total investment has been completed by 3 billion yuan, The funds paid have reached 2 billion yuan

.

According to the plan, the four alumina production lines are divided into five processes: raw material, dissolution, sedimentation, pressure filtration, decomposition and evaporation, which are accelerated simultaneously, and supporting the construction of thermal power projects

.

In the first half of the year, the region completed a fixed asset investment of 10.38 billion yuan, a year-on-year increase of 20.1%, maintaining a double-digit growth for five consecutive months, showing a good momentum of accelerating the volume of investment and injecting a strong driving force into high-quality development

.

The plant and storage area of bid section I of phase I of the comprehensive bonded zone began to attract investment and settled, and the civil construction of bid section II of phase I was seized to ensure the closure and operation by the end of the year

.

It will be sunny tomorrow at 25-38 ℃

. Erection Anchor One Sided

By holding investment promotion activities such as “Wanzhou trip of national well-known private enterprises”, Wanzhou District has newly signed 26 projects such as grain storage, grain warehousing and logistics, with a paid in capital of 2.78 billion yuan, an increase of 115.5%, and the development momentum continues to increase

.

” This year, Wanzhou has determined to implement 176 key projects

.

Deng Yongqin, deputy commander of the headquarters of wanbote aluminum new materials project, told reporters: “at present, the whole project is advancing in strict accordance with the construction period objectives set at the initial stage, the whole system has entered the equipment installation and commissioning stage, the overall progress of the five main processes has been completed by 65%, the No

.

This year, Wanzhou District has determined to implement 176 key projects that support and drive the construction of “one district, one hub and two centers”

.

At present, it has fully entered the decoration stage, and the overall image progress has reached more than 70%

.

Deng Yongqin said: “strive to power on and debug the equipment by the end of September and put into operation by the end of November.” Under the support and guidance of a number of key industrial projects such as wanbote aluminum new materials, in the first half of the year, the industrial investment of the whole region was 2.79 billion yuan, a year-on-year increase of 105.4%, 90.3 percentage points higher than that of the whole city, ranking the second in districts and counties of the whole city, driving the growth of fixed asset investment of the whole region by 16.5 percentage points

.

In order to accelerate the construction of the “one district, one hub and two centers” project, the whole region has established a project promotion mechanism

.

Among them, there are 30 ecological priority green development demonstration area construction projects, 21 national comprehensive transportation and logistics hub construction projects, 68 projects to improve the function of regional central cities, and 57 projects to build the economic center of the Three Gorges Reservoir area

.

In the first half of the year, Wanzhou Comprehensive Bonded Zone, which is of great significance for Wanzhou to build “one zone, one hub and two centers” and build a new inland open highland, also accelerated the pace of construction

.

Jiulong Park, Wanzhou economic development zone at the construction site of wanbote aluminum new material project with a total investment of 7.5 billion yuan, presents a hot scene of general assembly and construction

.

The investment volume increased month by month

.

The project department carried out wall chart operation and countdown to ensure that the project was completed and put into operation on schedule

.

1

.

Reporter: Li Zehong editor: Li Yanghong    Fan Qing   Chen Min   trainee   Edited by Mou Liuyue: original manuscripts of Liu yinglei, he Jiangdong and Chongqing Three Gorges financial media center are strictly prohibited without authorization

.

Since this year, Wanzhou District has focused on the construction of “one district, one hub and two centers” and spared no effort to promote projects and investment

.

In the first half of the year, 176 key construction projects completed an investment of 9.01 billion yuan, accounting for 42% of the annual plan

.