Earthwork excavation, stone breaking and outward transportation of the third layer
.
2
.
A total of 63 people were vaccinated, including 40 management personnel, 39 completed vaccination, and the remaining one was not vaccinated due to physical reasons; There are 16 on-site construction personnel, and 16 have been inoculated; There are 8 logistics personnel in total, including 7 who have completed vaccination and 1 who has completed the first injection
.
2
.
Epidemic prevention material reserve
.
There are 64 managers and workers in the project department
.
On August 1, 46 carts of stonework were unearthed, with a total of 13302 carts of stonework unearthed, totaling 166275 cubic meters
.
4
.
5
.
Daily temperature measurement of personnel entering the site
.
After June 27, 64 people have been tested for nucleic acid, and all of them are negative
.
Water level monitoring
1、 Weather conditions II
.
5、 Matters to be coordinated by the owner none
.
3、 Site construction and inspection 1
.
Epidemic prevention on site 1
.
Vaccination and nucleic acid testing
.
The second layer of northeast corner brace cushion concrete pouring is completed
.
3
.
4、 Subsequent construction plan 1
.
3
.
Daily pre shift education
.
The earth and stone excavation at the south side of the first and second bracing rooms, the second and third bracing rooms and the southwest corner of the third floor shall be broken and transported out
.
Construction of corner brace at northeast corner of the second floor
.