The earthwork at the corner brace at the northeast corner of the second floor shall be excavated and transported out
.
4
.
A total of 63 people were vaccinated, including 40 management personnel, 39 completed vaccination, and the remaining one was not vaccinated due to physical reasons; There are 16 on-site construction personnel, and 16 have been inoculated; There are 8 logistics personnel in total, including 7 who have completed vaccination and 1 who has completed the first injection
.
Daily temperature measurement of personnel entering the site
.
2
.
Vaccination and nucleic acid testing
.
Earthwork excavation, stone breaking and outward transportation of the third layer
.
3
.
2
.
The project team of the works Department went to the site to inspect and guide the work
.
3、 Site construction and inspection 1
.
3
.
The earth and stone excavation on the south side of the second and third support room of the third layer shall be broken and transported out
.
Water level monitoring
.
4、 Subsequent construction plan 1
.
2
.
1、 Weather conditions II
.
After June 27, 64 people have been tested for nucleic acid, and all of them are negative
.
5
.
Daily pre shift education
.
Epidemic prevention material reserve
.
Epidemic prevention on site 1
.
Construction of corner brace at northeast corner of the second floor
.
5、 Matters to be coordinated by the owner none
There are 64 managers and workers in the project department
.