General contracting project of medical complex building project of Longgang District Hospital of traditional Chinese medicine (Lot 2) project daily report on July 31, 2021

Epidemic prevention on site 1

.

Daily pre shift education

.

After June 27, 64 people have been tested for nucleic acid, and all of them are negative

.

Water level monitoring

.

2

.

Vaccination and nucleic acid testing

.

4

. Lifting Anchor

A total of 63 people were vaccinated, including 40 management personnel, 39 completed vaccination, and the remaining one was not vaccinated due to physical reasons; There are 16 on-site construction personnel, and 16 have been inoculated; There are 8 logistics personnel in total, including 7 who have completed vaccination and 1 who has completed the first injection

.

5

.

2

.

The earthwork at the corner brace at the northeast corner of the second floor shall be excavated, removed, transported and site leveled

.

1、 Weather conditions II

.

3

.

Epidemic prevention material reserve

.

4、 Subsequent construction plan 1

.

3

.

The earth and rock excavation at the south side of the second and third support rooms, the third and fourth support rooms and the southwest corner of the third floor shall be broken and transported out

.

5、 Matters to be coordinated by the owner none

.

          There are 64 managers and workers in the project department

.

Construction of corner brace at northeast corner of the second floor

.

Daily temperature measurement of personnel entering the site

.

Earthwork excavation, stone breaking and outward transportation of the third layer

.

On July 31, 9 carts of stonework were unearthed, with a total of 13256 carts of stonework unearthed, a total of 165700 cubic meters

.

3、 Site construction and inspection 1

.

2

.