The reconstruction and upgrading of Pushan Mantian road in Pingyang County is under intense construction

Halfen Channel

Among them, the section from Matougang to Pingyang branch of the Party School of Shanmen provincial Party committee is about 9 km long

.

At present, the construction progress has been completed about 70%

.

3000 people have joined the group to chat

.

The investment of phase I project is about 120 million yuan

.

The construction of asphalt concrete pavement of 9.2km from Matougang to the Party school branch of the provincial Party committee is about to be completed

.

The project was officially started in April 2019

.

Photo: at present, 40000 + people have paid attention to joining us                 New store publicity  / event planning  / All media promotion  / The hot spot broke the news.

.

At present, asphalt concrete pavement is being paved, and the pavement construction is expected to be completed in mid August

.

The traffic safety facilities will be followed up in time

.

In recent days, the phase I project of rural road upgrading project from Pushan to Mantian, a red tourist road in our county, is under intense construction

.

After completion, the road will be upgraded from the original 4-meter-wide single lane to a 6.5-meter-wide two-way lane, with additional security facilities along the line to create a real “four good” rural road

.

Beigang local exchange group makes Beigang warmer

.

After optimization and upgrading, the subgrade width of the road is 6.5 meters and 5cm thick asphalt concrete pavement is adopted, Two way two lane, design speed 20km / h

.

It is understood that phase 1 of the rural road reconstruction and upgrading project from Pushan to Mantian in Pingyang County has a total mileage of about 17 kilometers, including 2.1 kilometers of branch line 2 (Matougang to Datun), 7.1 kilometers of branch line 3 (Datun to the Party school branch of the provincial Party committee), and 7.8 kilometers of main line (Datun to Mantian Forest Park)

.

It is expected to complete the construction of this section in August, and the subgrade works of the remaining Datun Mantian Forest Park section are basically completed, The whole line was originally planned to be completed by the end of November, but now it is expected to be completed in October

.