10.8 billion metro construction general contracting bidding! Come on

Qualification requirements of the bidder 3.1 The bidder is required to meet the following conditions in this bidding: 3.1.1 the bidder is required to meet the following qualification conditions

.

Project overview and bidding scope 2.1 construction location: Chongqing 2.2 project overview and construction scale: phase II project of line 15 starts from Zengjia station, passes through University City Middle Road station, University City South Station, Chenjiaqiao station, University City North First Road station, science city station, logistics park north station, wellhead station, Lixue Road station, Jinshan Temple Station and happy valley station, The terminal is Jiuqu Hedong station of phase I of line 15

.

2.4 bidding scope: the mileage stake number of the bidding project is yk35 + 575 ~ yk53 + 573, and the length of the line is 18.0km (including the section works and stations from Logistics Park North Station (excluded) to Jiuquhe east station (excluded), the entrance and exit line section of Jiuquhe parking lot, Zhongliangshan tunnel and liaojiaxi special bridge, etc.), corresponding to cq15tj16 ~ cq15tj19 and other four construction sections

.

The total construction period of Chongqing rail transit line 15 phase II project is planned to be 63 months

.

Com)

.

3.3 participation in this bidding agreement in order to ensure the smooth implementation of the project, the bidder can bid for two general construction contracts, including the general construction contract of Chongqing rail transit line 15 phase II project (yk20 + 351 ~ yk35 + 575) and the general construction contract of Chongqing rail transit line 15 phase II project (yk35 + 575 ~ yk53 + 573), However, it can only become the first candidate for winning the bid (the bid winner) of one of the general construction contractors

. Magnetic Box Adapter

The project has met the bidding conditions, and now the general construction contract of Chongqing rail transit line 15 phase II project (yk35 + 575 ~ yk53 + 573) is subject to public bidding

.

The total length of the line is about 32.8km, including 30.5km underground line (including open excavation section) and 2.3km elevated line

.

Before bidding, the bidder can visit Chongqing public resources trading network (www.cqggzy

.

3.2 the project accepts the consortium bidding, and the consortium members shall not exceed 5

.

Notice of bidding for general contracting of Chongqing rail transit line 15 phase II project (yk35 + 575 ~ yk53 + 573) 1

.

Relevant risks shall be fully considered by the tenderer, and the tenderer shall not make any claim against the tenderee

.

663, and the owner of the project is Chongqing Railway (Group) Co., Ltd, The construction fund comes from state-owned funds, the proportion of project investment is 100%, and the tenderee is Chongqing Railway (Group) Co., Ltd

.

2

.

From the 44th month, the general contractor of the construction will unconditionally provide construction site and construction conditions for subsequent works; In the 44th month, the track laying construction of main line stations, sections, Zhangjiawan depot and access line sections of phase II project of rail transit line 15 will be carried out, with a construction period of 8 months

.

Acquisition of bidding documents 4.1 the whole process of electronic bidding is adopted for the bidding project

.

Specifically, it includes: (2) the project may have risks such as scope change, scale change, engineering quantity change, major change, work preparation change of each work site, etc

.

The line goes out of the North Station of logistics park to liaojiaxi bridge, and passes through Xiangfan Chongqing railway, Chongqing Guiyang railway, Chongqing Guizhou railway, viaduct of Caidong connecting line of Suining Chongqing railway, Weijing down line of Suining Chongqing railway, Weijing up line of Suining Chongqing railway and Chengdu Chongqing high speed railway viaduct

.

2.5 construction period requirements: 1523 calendar days, defect liability period requirements: 24 months

.

Bidding conditions the bidding project Chongqing rail transit line 15 phase II project has been approved by Chongqing development and Reform Commission as yfgjt [2021] No

.

The bidding project is planned to start in September 2021, and the contracted project is planned to be implemented and completed in 1523 calendar days according to the contract

.

see article 1.4.1 in the pre attached table of Chapter II instructions to Tenderers of the bidding document for details

.

There are 11 stations in the whole line, including 1 elevated station and the rest are underground stations

.

3

.

In the bidding activities, if the bidder is disqualified from bidding or winning the bid due to its own reasons, the bidder shall bear relevant responsibilities; If the bidder has been determined as one of the successful bidders of general construction contract of Chongqing rail transit line 15 phase II project, it will no longer be determined as the successful bidder of another general construction contract of Chongqing rail transit line 15 phase II project\ 4

.

Zhangjiawan vehicle base and Zhangjiawan main substation are set

.

The line is double track, adopts the right-hand running system, adopts the urban rail express vehicles with the maximum running speed of 140 km / h and 25 kV AC system, adopts 6-car marshalling, and the initial allocation is 17 trains / 102 vehicles

.

Please pay attention to the WeChat public official account of the “highway and railway engineering exchange platform”, the largest highway and Railway Employee exchange platform in the country, and free recruitment and job search information

.

If the bidder is the one who has passed the review and offered the lowest price among the two general construction contracts at the same time, the bid evaluation committee shall recommend it as the first bid winner candidate for the general construction contract of Chongqing rail transit line 15 phase II project (yk35 + 575 ~ yk53 + 573) (it will no longer be recommended as the bid winner candidate in another general construction contract project), The first candidate for winning the bid of another general construction contract shall be supplemented by the bidder who has passed the evaluation and has the lowest quotation

.

From the 46th month, the general contractor of the construction will unconditionally provide the construction site and construction conditions for the power supply system; Starting from the 49th month, the general construction contractor unconditionally provides construction sites and construction conditions for post station works such as electromechanical equipment and communication signals of the whole line

.

2.3 estimated contract amount of the bidding project: 5.79 billion yuan

.

See article 1.4.1 and 1.4.2 of the pre attached table of Chapter II instructions to bidders in the bidding document for specific requirements

.

See article 1.4.1 of the pre attached table of Chapter II instructions to bidders in the bidding document for details: it has the effective “Railway Engineering”, “Municipal Public Engineering” and “construction engineering” issued by the competent construction administrative department Any one of “highway engineering”, “water conservancy and Hydropower Engineering” and “port and waterway engineering” with special grade qualification for general construction contracting and two of them with grade I or above qualification for general construction contracting; 3.1.2 the tenderer shall also have corresponding construction capacity in terms of personnel, equipment, capital, etc

.

The construction period of the general contracting civil works is 50 months

.