In one of the rooms under construction in building 9, the reporter saw that the distribution box has not been installed, and some water pipes have not been connected at present“ Yuanfang construction is bankrupt
.
Sun said that there are only some installation works left of the first 7 to 9 buildings to be delivered, and the backfill project will be completed in the past two days
.
Many owners have the same findings as Ms
.
The reporter learned that Changsha Yongshi rose international community is divided into two contractors for construction, of which buildings 1 to 13 are China Construction Third Bureau and buildings 14 to 22 are round square construction
.
Yang said, “no wonder the construction progress of the community has become relatively slow since years later, and there are few construction people.” When passing the container room near the gate of the community, one of the owners told reporters that years ago, there were many construction workers’ clothes hanging here, and now we can’t see this scene
.
(hereinafter referred to as “Yuanfang construction”) in charge of buildings 14 to 22 of the community had applied for bankruptcy as early as January this year
.
” On July 27, the owners found Mr
.
Among them, the first batch of houses to be delivered is 7 to 9, and the delivery deadline is August 31
.
Mr
.
Yang is the owner of building 21 of Changsha Yongshi rose international community
The 190-240 flat floors are about to be launched
.
However, due to the need to pass the completion filing form approved by the government department, the delivery time was postponed to November 30“ Reasonably speaking, the owner needs to be informed in writing 90 days in advance of the delayed delivery
.
Sun finally said that from this negotiation meeting, the community will return the original round square construction workers within 20 days and allow the new construction unit to enter the site for construction
.
You have to give me time to solve this problem
.
Yang“ There is no one on the construction site, and the delivery of the house is far away
.
1 middle school and double school district, downstairs is the park, and send the whole house air conditioning + electrical appliances, 95 ~ 135 square meters! A small number of houses! Direct subscription! Binjiang mansion 1913: within the first ring road of Changsha City, there are river views, double subway entrances and double famous schools
.
The second batch of houses to be delivered is 18 to 22, and the delivery deadline is October 31
.
Excellent real estate consultants recommend Sunshine City Shangdong Bay: Yuhua main city red plate, changtangli + Changsha No
.
In response to the owners’ question of “when to resume work”, Mr
.
On July 27, there was no construction on the construction site of Changsha Yongshi rose international community
.
Xiaoxiang Morning Post reporter inquired through the enterprise investigation official website that there are two pieces of bankruptcy and reorganization information of Yuanfang construction
.
” Mr
.
Sun also said that he had negotiated with the new contractor, “after the meeting yesterday morning, a new construction unit entered the site in the afternoon
.
Sun said that the previous meeting said “try to solve it in 15 days”“ I can’t guarantee that it will be solved in 15 days
.
The reporter walked into the construction site and found that part of the open space on the road of the community is still under “earthwork backfilling”, and the greening has not been completed
.
She said that when she passed the construction site in early July, she found that there were very few construction personnel, sometimes even “only individual personnel”
.
” Mr
.
On the same day, the developer promised that the construction of the first batch of houses would be completed on August 31
.
If this goes on, the house will certainly not be delivered on time.” Ms
.
There are still some projects not done on the road and inside the house
.
The owner has no choice but to complain through Sina black cat platform
.
Before that, the owner representative of Changsha Yongshi Rosa international community, Mr
.
The developer’s previous commitment has not been fulfilled, so we don’t trust it
.
Yang said that the construction of Yuanfang had hardly started, and many projects on the developer’s schedule had not been completed on time“ Because of the bankruptcy of Yuanfang construction, the construction of 1 to 13 houses originally constructed by China Construction Third Bureau has also been affected
.
The latest article is published on July 8, 2021, and the latest trial procedure is “bankruptcy”【 [site] the water and electricity system in the house has not been completed
.
Ms
.
The construction of strong current system will also be arranged before August 10“ If I don’t solve the problem in 20 days, you can come to me
.
Changsha Ruyuan: Lugu hairy embryo house, with a unit price of 8 characters, high subway entrance + room acquisition rate, Vanke property, hot selling! Hengduhui Plaza: the red plate of high-speed railway exhibition new town, the gateway of high-speed railway, the bridgehead of free trade zone, double subway + school + business, 112-178 square meters, hot and sincere registration!.
.
Gu, the owner of building 11 in the community, said that he bought the building in early 2020
.
Mr
.
When can we have a new contractor in our community? When can we fully resume work? When can bankruptcy disputes be settled? ” Community owners raised the above questions【 [developer] the new contractor has been checking the quantities
.
also affected the construction of another construction unit, China Construction Third Engineering Bureau
.
Recently, they learned that Hunan Yuanfang Construction Co., Ltd., which is responsible for the construction of buildings 14 to 22 in the community, has applied for bankruptcy, and no new construction party has taken over
.
Sun, head of Hunan regional company of Yongshi group, a community developer, and the community neighborhood office held several associations
.
Since July, the owners of Changsha Yongshi rose international community have found that the number of construction personnel in the community has decreased sharply and almost turned into a shutdown state
.
Some owners questioned that the bankruptcy of Hunan Yuanfang Construction Co., Ltd
.
“Now there are few workers in the whole community, which is no different from the shutdown state
.
“At the beginning of a period of time, the construction was very rapid and made rapid progress, which is completely different from what we see now”“ Only recently did we know that Hunan Yuanfang Construction Co., Ltd
.
The most recent consultation was on July 26
.
” Source: Xiaoxiang Morning Post long press the QR code below to add small friends
.
” One of the owners told reporters that in the construction schedule for the remaining works of phase III block B 7-9# building issued by him, the end date of “roof earthwork backfilling” was July 19, and the end date of “basement roof drainage and storage layer processing” was July 17, but “it’s the 27th, and neither of these two items has been completed”, And “this is already a construction schedule after the delay”
.
” Ms
.
Sun said that since he had the confidence to say so, it was because the leaders of the company headquarters had met with the new construction personnel the day before
.
Sun again and sought an explanation on “when can the construction be resumed”
.
We only knew it more than a month before the deadline
.
Photo / reporter man Yankun [owner] there are few workers in the whole community
.
What are the facts? Xiaoxiang Morning Post “man Ge rights protection” column reporter went to the scene to find out
.
They have begun to count the quantities on site, and some people counted the quantities in the community this morning”
.
There are still problems such as incomplete installation of distribution boxes and incomplete connection of water pipes in the first batch of buildings 7 to 9 planned to be delivered before August 31
.
After some negotiation, Mr
.