An autumn letter from home is presented.
Wanjing family letter to the dear Wanjing family: if you see the letter, how are Zhan Xin! September comes in the twinkling of an eye, the autumn is crisp, the harvest is beautiful, the ideal life is closer and closer, and the appearance of home is clearer.
May time treat you gently as usual and share every step of your growth with you.
04 construction progress of outdoor public area construction of garage structure main body construction of central and western gate main body every time we wait, we hope to meet the most beautiful scenery.
Please look forward to the progress of subsequent projects.
■ progress broadcast 41#42#46# building: 60% of the staircase step construction is completed, and the public area decoration is ready for construction.
■ progress broadcast 45#50# building: interior wall painting is under construction.
41#42#46# building: the external wall insulation is completed by 50%, and the external wall coating is under construction; The installation of outer window frame is completed by 60%.
Your warm and happy new home is steadily “growing”.
02 broadcast of main construction progress ■ 36#37#38# building: 60% of the external wall insulation is completed, and the external wall coating is under construction; The installation of outer window frame is completed by 60%.
■ progress broadcast 41#42#46# building: after the building is cleaned, the radiant heat materials are mobilized to prepare for construction.
We have common expectations for a better life in the future.
03 indoor construction progress broadcast ■ 36#37#38# building: radiant heat in the building is under construction.
45#50# building: the outer window frame is being installed.
■ progress broadcast 41#42#46# building: the external wall insulation is completed by 50%, and the external wall coating is under construction; The installation of outer window frame is completed by 60%.
■ progress broadcast 45#50# building: the outer window frame is being installed.
Wanjing lizhiwan project August 2021 。.
01 overall construction progress 36#37#38# building: 60% of external wall insulation is completed, and the construction of external wall coating is in progress; The installation of outer window frame is completed by 60%.
■ progress broadcast 36#37#38# building: 60% of the staircase step construction is completed, and the public area decoration is ready for construction.