Construction technology development and Reform Commission: government projects shall not be advanced by the construction unit! Do not arbitrarily reduce the scale of government investment! Strictly implement the “four project systems”

However, there are still some projects with lax management and inadequate implementation of relevant management regulations, resulting in decreased project quality and increased potential safety hazards

.

Government invested projects shall submit project proposals, feasibility study reports and preliminary designs for approval in accordance with relevant state regulations

.

For the height limit of buildings, the Ministry of housing and urban rural development recently issued the opinions on strengthening the green and low-carbon construction of the county, strictly implement the “four project systems” and the project legal person responsibility system, and the project unit and legal representative shall take overall responsibility for the safety and quality of the project construction

.

712 of the State Council / regulations on government investment shall enter into force on July 1, 2019, prohibiting “advance construction”: government investment projects shall not be advanced construction by construction units

.

To implement the project supervision system, the supervision unit shall earnestly perform the supervision responsibilities, especially strengthen the supervision and inspection of key processes, important parts and concealed works

.

NOCITCE changed the push rule because of WeChat official account

.

The bid winning price determined by project bidding shall reflect the reasonable cost requirements and eliminate the safety and quality problems caused by low cost

.

Timely completion final accounts: after the completion of government investment projects, the completion acceptance shall be carried out in accordance with the relevant provisions of the state, and the completion financial final accounts shall be handled in time after the completion acceptance is qualified

.

In the planning and site selection stage, the project site selection scheme shall be optimized to avoid sensitive areas with high risk as far as possible

.

When purchasing goods, projects and services from small and medium-sized enterprises, organs and institutions shall pay within 30 days from the date of delivery of goods, projects and services; If otherwise agreed in the contract, the maximum payment period shall not exceed 60 days

.

910 development and Reform Commission of all provinces, autonomous regions, municipalities directly under the central government and cities specifically designated in the state plan, Xinjiang production and Construction Corps: in recent years, all localities have continuously strengthened the management of construction projects in infrastructure and other fields, and the level of project safety and quality has been continuously improved

.

Implement the bidding system, do a good job in project bidding in accordance with the requirements of the bidding law, regulations on engineering projects subject to bidding, regulations on the scope of infrastructure and public utility projects subject to bidding, and take the mandatory safety and quality standards as the substantive requirements and conditions of the bidding documents

.

724 of the State Council  /《 The funds required for government investment projects shall be in place in accordance with the relevant provisions of the state and shall not be advanced by the construction unit

. Short Waved Anchor

Enterprise investment projects shall go through the approval or filing procedures in accordance with the catalogue of investment projects approved by the government and other relevant provisions

.

Strictly implement the notice of the Ministry of housing and urban rural development and the national development and Reform Commission on Further Strengthening the management of urban and architectural features, and manage super large public buildings, super high-rise buildings and buildings in key sections as major urban construction projects.

.

Attached original: Notice of the national development and Reform Commission on strengthening the management of infrastructure construction projects to ensure the safety and quality of projects fgtzg [2021] No

.

Strict project cost and construction fund management

.

If the construction unit is required to advance funds for the construction of government invested projects, it shall investigate the responsibilities of organs and institutions in accordance with laws, administrative regulations and relevant provisions of the state

.

728 of the State Council  /《 The regulations on ensuring the payment of funds by small and medium-sized enterprises shall come into force on September 1

.

Strictly control the review of super high-rise buildings, and strictly implement the seismic fortification approval system for super high-rise buildings above 100 meters, which is appropriate to the urban scale and spatial scale and the fire rescue capacity; Strictly restrict the construction of new buildings more than 250 meters

.

Implement the contract management system, conclude contracts for survey and design, construction, equipment and material procurement and project supervision of construction projects according to law, and clarify safety and quality requirements and liability for breach of contract

.

In order to further strengthen the management of infrastructure construction projects, adhere to quality first and ensure the safety of people’s lives and property, the relevant matters are hereby notified as follows: 1

.

When signing a written project construction contract with the general contractor according to law, the construction unit shall agree on the measurement period of project funds, the settlement method of project funds progress and the allocation period of labor costs, and agree on labor costs in accordance with the requirements of ensuring the timely and full payment of migrant workers’ wages

.

Decree No

.

In case of any dispute between the construction unit and the general contractor or between the contractor and the subcontractor over the project quantity, quality and cost, the construction unit shall not allocate the labor cost in the project payment due to the dispute in accordance with the provisions of Article 24 of these regulations, and the general contractor shall not pay wages in accordance with the provisions due to the dispute

.

This notice shall go into effect as of the date of printing and distributing

.

If both parties have agreed on the interest rate of overdue interest, the agreed interest rate shall not be lower than the market quotation interest rate of one-year loan at the time of conclusion of the contract; If no agreement is made, the overdue interest shall be paid at the daily interest rate of 0.05%

.

If it is really necessary to build, the construction scheme shall be reviewed in combination with special demonstration such as fire control, and reported to the Ministry of housing and urban rural development for the record; No new super high-rise building more than 500 meters shall be built

.

On July 6, the national development and Reform Commission issued the notice on strengthening the management of infrastructure construction projects to ensure the safety and quality of projects

.

The construction unit shall provide the project payment guarantee to the construction unit

.

The construction unit shall timely allocate the project funds in accordance with the contract, timely and fully allocate the labor costs to the special account for migrant workers’ wages, and strengthen the supervision of the general construction contractor to pay migrant workers’ wages in full and on time

.

The funds required for government investment projects shall be in place in accordance with the relevant provisions of the state

.

Decree No

.

Strengthen project audit (1) standardize the implementation of project approval (approval and filing) procedures

.

Order No

.

The allocation period of labor cost shall not exceed 1 month

.

The feasibility study report shall conduct in-depth analysis and evaluation on major problems related to project safety and quality, and put forward countermeasures

.

Projects that fail to perform the examination and approval (approval and filing) procedures as required and do not meet the specified construction conditions shall not start construction( 2) Further strengthen the project quality management in the preliminary work stage

.

It is not allowed to arbitrarily reduce the construction period: the construction period of government invested projects shall be reasonably determined and strictly implemented in accordance with the relevant provisions of the state, and no unit or individual shall illegally intervene

.

If you don’t want to miss the highlight of this official account, please put the public number of construction technology as the star sign and click “collect”, “look at” and “Zan” at the end of the text, so that each new article will appear in the subscription list at the first time

.

Star setting: enter the official account home page, click on the top right corner, click “set star”, and yellow star will appear next to the official account name (Android and iOS user operation is the same)

.

//Wechat public account setting prompt///   The official account is official

.

If the construction unit fails to timely allocate the project funds in accordance with the contract, resulting in the arrears of migrant workers’ wages, the construction unit shall advance the arrears of migrant workers’ wages to the extent of the outstanding project funds

.

It is strictly prohibited to transfer, occupy or misappropriate government investment funds

.

The project unit shall improve the quality of the preliminary work of the project and ensure that the depth of the project proposal, feasibility study report, preliminary design, project application report and other documents meet the specified requirements

.

The preliminary design shall strictly implement the mandatory standards for engineering construction, put forward safety and quality protection measures, and put forward corresponding requirements for the construction scheme( 3) Strict examination of super high-rise buildings

.

The construction unit shall not advance the construction, and shall not arbitrarily reduce the investment scale specified in the government investment plan

.

In strict accordance with the relevant provisions of the regulations on government investment and the regulations on the administration of the approval and filing of enterprise investment projects, the procedures for the approval (approval and filing) of investment projects shall be performed

.

It shall not change the legal representative or main person in charge, perform the internal payment process, or wait for the reply of completion acceptance and final account audit without agreement in the contract, If a government organ, institution or large enterprise refuses or delays in paying the funds of a small and medium-sized enterprise, it shall pay overdue interest

.