On August 2, 2021, Pucheng Chuangshi Energy Co., Ltd
.
Pipeline civil engineering excavation, installation, pipe laying, pipe welding, replacement of valves of Sijihuacheng branch pipeline, and sweeping of pipeline welding of Phoenix branch pipeline Pay attention to us and consult more Know it earlier
.
Thermal service Tel: 0913-7234596 ↓ click below“
.
Chengnan branch line mainly involves the South auxiliary road of Xincheng Avenue (Renmin Road to Jiefang Road) and the west auxiliary road of Jiefang Road (Xincheng avenue to Kaiyuan Street), with a total length of about 1000m
.
Construction of pipeline reconstruction and valve replacement in Pucheng central heating urban area began
.
began to reconstruct the south branch pipeline and Phoenix branch pipeline
.
At present, the pipeline civil engineering has been excavated to Pucheng County Government Service Center, and the pipeline locomotive installation has also started laying, matching and welding