The foundation pit of No
.
2) There are 396 SMW construction method piles for the auxiliary enclosure structure of Liujia station, with a total of 396 open piles, with a completion rate of 100%
.
10) The third concrete support of the main structure of Baofeng village station is 67 in total, 67 in total, with a completion rate of 100%
.
1 wind Pavilion and entrance and exit d), of which 0 were completed today and 68 were opened, with a completion rate of 41.0%
.
6) There are 190 uplift piles for the main enclosure structure of baofengcun station, with a total of 190 piles, with a completion rate of 100%
.
Implementation of Risk Engineering 1
.
1 wind Pavilion of the auxiliary enclosure structure of gongjiacun station (No
.
The deepest foundation pit is 11.89m
.
B entrance and exit and No
7) There are 76 dewatering wells in the main structure of baofengcun station, with a completion rate of 100%
.
5) The earth excavation of the foundation pit of the auxiliary structure of Baofeng village station is 9400 m3, with a total of 8600 m3 (including 4200 m3 for entrance C, 3900 m3 for entrance D and 500 m3 for fire pump house), with a completion rate of 91.5%
.
3) There are 269 isolation piles for the main enclosure structure of Baofeng village station, with a total of 269 open piles, with a completion rate of 100%
.
At present, the excavation has been completed, with a total excavation of 3900 m3
.
13) The fourth steel support of the main structure of Baofeng village station is 36 in total, with a completion rate of 100%
.
The soil layers within the excavation depth of the foundation pit include quaternary artificial fill, 2-2 peat soil, 3-3 silty clay, 4-3 silty soil, etc
.
The maximum depth of the foundation pit is 12.28m
.
The excavation of the deep foundation pit of the fire pump house of the auxiliary structure of Baofeng village station belongs to class II risk
.
3) There are 34 steel supports for the first auxiliary structure of Baofeng village station, including 28 open ones (including 15 at entrance C and 13 at entrance d), with a completion rate of 82.3%
.
5
.
4) There are 161 underground diaphragm walls of the main enclosure structure of baofengcun station, with a completion rate of 100%
.
The deepest foundation pit is 11.37m
.
2 wind Pavilion of the auxiliary structure of Liujia station: the excavation was started on April 20, 2021
.
The maximum depth of the foundation pit is 7.973m
.
02 risk control 1 risk situation in the implementation cycle 1
.
3 risk engineering deformation index 1
.
5) There are 134 lattice columns in the main enclosure structure of Baofeng village station, with a completion rate of 100%
.
Daily report of the third project management department of Kunming Metro Line 2 phase II general contracting project on August 31, 2021 Tuesday Qing 01 project overview 1
.
14) The total earthwork excavation of the main structure of Baofeng village station is 243368m ³, Kailei 243368m ³, The completion rate is 100%
.
2
.
The excavation of the deep foundation pit of No
.
12) The third steel support of the main structure of Baofeng village station is 18 in total, with a completion rate of 100%
.
2) There are 6814 pieces of foundation reinforcement for the main enclosure structure of baofengcun station, with a completion rate of 100%
.
The base is mainly located in peat soil layer
.
The foundation pit is protected by SMW construction method pile
.
Auxiliary structure of the Convention and Exhibition Center Station 1) there are 4818 triaxial mixing piles for the auxiliary enclosure of the Convention and Exhibition Center Station, with a completion rate of 100%
.
Foundation pit of auxiliary structure fire pump house of Baofeng Village Station: preparation stage before excavation
.
3) there are 834 bite piles in total and 834 in total, with a completion rate of 100%
.
The soil layers within the excavation depth of the foundation pit include quaternary artificial fill, 2-2 peat soil, 3-3 silty clay, 4-3 silty soil, etc
.
3
.
4
.
4) The earth excavation of the foundation pit of the ancillary structure of the Convention and Exhibition Center station is 83184m in total ³, Kailei 83184m ³, The completion rate is 100%
.
Auxiliary structure of Liujia station 1) there are 207 uplift piles in total for auxiliary enclosure structure of Liujia station, with a completion rate of 100%
.
4
.
4
.
1 wind pavilion has been completed), with a completion rate of 59.4%
.
2) There are 45 uplift piles for the auxiliary enclosure structure of Baofeng village station, with a total of 45 piles (including 22 at entrance C, 17 at entrance D and 6 at fire pump house), with a completion rate of 100%
.
3
.
1 wind Pavilion of auxiliary structure of Liujia station: the excavation was started on May 1, 2021
.
The excavation of deep foundation pit at the entrance and exit of Annex C of Baofeng village station belongs to class II risk
.
The foundation pit is protected by SMW construction method pile
.
5) The earth excavation of auxiliary structures of Liujia station is 25258m in total ³, Kailei 25258m ³, The completion rate is 100%
.
The base is mainly located in peat soil layer
.
1 wind Pavilion of the auxiliary structure of Liujia station belongs to class II risk
.
4) The second steel support of the auxiliary structure of Liujia station is 40 in total, with a completion rate of 100%
.
The soil layers within the excavation depth range of foundation pit include 3-3 peat soil and 5-2 silty sand
.
2
.
The soil layers within the excavation depth of the foundation pit include 3-3 peat soil and 5-2 silty sand
.
Foundation pit at entrance and exit of auxiliary structure C of Baofeng Village Station: there is no deformation index at present.
.
1 wind Pavilion and D entrance and exit), and there are 79 in total (No
.
2
.
2) The three-axis base reinforcement of No
.
The foundation pit at the entrance and exit of ancillary structure d of Baofeng Village Station: the excavation was started on July 19, 2021
.
2) There are 97 diaphragm walls in total and 97 in total, with a completion rate of 100%
.
1 wind Pavilion of the auxiliary enclosure structure of gongjiacun station is 275 in total, with a completion rate of 100%
.
5
.
the base is mainly located in peat soil layer, and the foundation pit is protected by bite pile
.
2 wind Pavilion belongs to class II risk
.
11) There are 18 second steel supports for the main structure of Baofeng village station, with a completion rate of 100%
.
8) The first concrete support of the main structure of Baofeng village station is 77 in total, with a completion rate of 100%
.
5
.
At present, the excavation has been completed, with a total excavation of 4200 m3
.
4) There are 32 steel supports for the second auxiliary structure of baofengcun station, with a total of 26 open (including 14 at entrance and exit C), with a completion rate of 81.3%
.
Auxiliary structure of Baofeng Village Station 1) there are 278 bite piles for auxiliary enclosure structure of Baofeng village station, with a total of 278 open piles (118 at entrance C, 101 at entrance D and 59 at fire pump house), with a completion rate of 100%
.
3) There are 77 steel supports for the first auxiliary structure of Liujia station, with a completion rate of 100%
.
3) There are 166 SMW construction method piles for No
.
Auxiliary structure of gongjiacun station 1) there are 133 triaxial cement soil mixing piles for the auxiliary enclosure structure of gongjiacun station (No
.
9) The second concrete support of the main structure of Baofeng village station is 67 in total, with a completion rate of 100%
.
the base is mainly located in the silty soil layer, and the foundation pit is protected by bite piles
.
The excavation of deep foundation pit at the entrance and exit of ancillary structure d of Baofeng village station belongs to class II risk
.
The maximum depth of the foundation pit is 10.659m
.
The excavation of deep foundation pit at the entrance and exit of auxiliary structure B of Liujia station and No
.
At present, the excavation has been completed, with a cumulative excavation of 9800 m3
.
Foundation pit of No
.
The soil layers within the excavation depth range of foundation pit include quaternary artificial fill, 2-2 peat soil, 3-3 silty clay, 4-3 silty soil, etc
.
3
.
Main structure of Baofeng Village Station 1) there are 1010 pieces of groove wall reinforcement of main enclosure structure of Baofeng village station, and 1010 pieces have been opened, with a completion rate of 100%
.
2
.
Foundation pit at the entrance and exit of auxiliary structure C of Baofeng Village Station: the excavation was started on July 6, 2021
.
The base is mainly located in peat soil layer, and the foundation pit is protected by bite pile
.
15) There are 14 sections in total for the bottom plate construction of the main structure of baofengcun station, including 14 sections in Kailei, with a completion rate of 100%; There are 14 sections in the middle plate, including 14 sections, with a completion rate of 100%; There are 14 roof sections in total, including 14 sections, with a completion rate of 100%; There are 14 sections of the side wall on the second floor of the basement, and 14 sections have been completed in total, with a completion rate of 100%; There are 14 sections of the side wall on the first basement floor, and 14 sections have been completed in total, with a completion rate of 100%
.
At present, the excavation has been completed, with a total excavation of 8000 m3
.