It doesn’t matter whether the general contractor has a big package or not
.
Party A agrees to give us 10% of the premium
.
If the list item changes, the price shall also be re combined, but it must be approved by the owner or the supervisor
.
■ 5: How to solve the increase or decrease of quantities caused by incorrect quantities in the bill of quantities? ■ Answer: according to the specific requirements of the contract for settlement terms
.
Click above 👆 ■ 1: After the completion of the project, Party B made settlement according to the later changed construction drawings, and the settlement still adopts the list pricing method
.
Therefore, our settlement shall be carried out at the unit price approved by Party A, but the auditor only agrees to adjust the cost of main materials and does not agree to adjust the quota content and labor cost
.
The change of the list item has two parts: the first is the change of the work quantity, and the second is the change of the work content
.
In addition, the construction drawings and the drawings at the time of bidding change greatly, which does not meet the conditions specified in the bidding documents
.
■ 9: For the project of mechanical large-scale excavation, there is no agreement in the contract and no special requirements of Party A
.
However, Party B insists on settlement in the form of list on the ground that there is a bid winning price in the list, and does not agree to adjust the comprehensive unit price and measure fee
.
Therefore, it is decided to conduct the audit in the way of quota pricing and settlement, recalculate all the settlement construction drawings, and recalculate the measure cost
.
Therefore, when both parties confirm the settlement according to the fixed price, whether it is signed or not, if so, it is correct regardless of the price
.
In addition, the claims arising from the termination of the contract should be increased
.
According to the contract, Party A’s signature is recognized
.
The final cost excluding the materials supplied by Party A is 10 million
.
The second is the specific requirements for design change or visa according to the contract
The construction party believes that the original contract labor premium is reduced to 150000 yuan based on the budget of 180000 yuan, and the labor insurance premium actually completed should be reduced in the same proportion, and should be reduced in proportion based on the labor insurance premium of 80000 yuan? How should such situations be handled? Under the above circumstances, the actual settlement total price of the project is far less than the total price of the project at the time of contract awarding, and the cost of temporary facilities is also reduced according to the actually completed quantities
.
■ 3: For the bidding project with bill pricing mode, how to deal with several problems when handling the completion settlement (the contract indicates that the settlement shall be based on the actually completed quantities, i.e
.
The settlement price is 12 million yuan, and there is another negotiation change of 2 million yuan (the as built drawings and completion acceptance reports are not handled for the project, and many changes in materials and practices are not signed)
.
■ 8: If the general contractor subcontracts the waterproof works to others, and the other party has the unit price details (material cost + labor cost) and Party A shall sign for approval
.
The approved price obtained is much lower than the settlement price of Party B
.
If not, both parties have to re determine the settlement method before handling the settlement
.
If there is no requirement, the price shall be combined according to the actual material price
.
The first one is adjusted completely according to the limit requirements of the price of individual subitems
.
■ 2: During list settlement, how to settle after adjustment of material price difference and provisional estimate and adjustment of list sub items according to the contract? The price after adjustment of material price difference and provisional estimate can be implemented according to the contract, but if the contents included in the list items are changed, how to deal with the increase or decrease? In addition, if Party A stipulates that the price of the changed single sub item will not be adjusted within a certain limit, how to avoid the risk? At the same time, does this clause apply to the price after the change of the contents of the above list? ■ A: during settlement, the adjustment of material price difference and provisional estimate should be in accordance with the contract
.
Generally speaking, the settlement is based on the actual situation, so there is no problem of reducing the temporary facilities cost in proportion
.
As for the materials provided by Party A, the construction unit only keeps the storage fee when returning them
.
I don’t know how to deal with such situations according to the industry rules? ■ A: this problem belongs to the settlement method for the completed project after the termination of the contract
.
If it is other schemes, the consent of the construction unit and the supervisor must be obtained when changing the scheme
.
After the contract is signed, if there is no clear provision, the measures cannot be changed, which is the cost that must be incurred to complete the qualified project
.
When both parties terminate the contract and settle the actually completed project, only 80000 yuan of labor insurance premium shall be taken according to the normal charging standard
.
The measures shall analyze whether the change is caused by the change of the quantities
.
Now we want to return the materials supplied by Party A
.
In principle, it shall be in accordance with the requirements of the contract for the settlement of contract termination
.
Generally, both parties negotiate settlement and supplement detailed contract terms before settlement
.
In addition, there are 5 million materials supplied by Party A
.
How should such differences be judged? ■ A: the focus of this question is whether to use quota pricing and settlement method
.
■ 4: The group price of the comprehensive unit price of the new project in the bidding project settlement
.
If there is a clear agreement in the contract to settle according to the quota, no matter whether Party A signs or not, evidence of changing the settlement basis must be found
.
■ 6: Now there is a project, which is priced by bill of quantities
.
The principle is 2001 fixed market price and fixed quantity
.
Whether the material price is based on the material price quoted by the construction unit during bidding or the actual material price during project construction
.
If there is no requirement, it is necessary to analyze whether this contract type is an open contract or a closed contract
.
However, according to the construction party, the cost of temporary facilities has been invested at one time according to the project scale in the early stage of construction, and the temporary facilities exceed the construction period agreed in the contract due to the construction party, and there is no residual value for the temporary facilities, so the cost of temporary facilities shall remain unchanged according to the original contract budget
.
whether the bill error is exceeded or not): ⑴ if the quantities are increased or decreased, the divisional project cost can be calculated according to the bidding unit price; Should the measure fee in the original bid price be adjusted accordingly? (2) after the direct fee or measure fee is adjusted, should the fees in the original bid be adjusted accordingly? (3) is the tax adjusted accordingly? ■ Answer: after the increase or decrease of the quantities, the sub items and sub items shall be adjusted according to the actual situation
.
If there are signing procedures, they should be increased
.
■ 7: I
.
I think the statement of the construction party is reasonable
.
For example, the original bidding basis is the belt foundation, which is later changed to the full hall foundation
.
During the audit of this project, the consulting company based on Party B’s settlement quotation is inconsistent with the contract price, and the comprehensive unit price and method of settlement are not consistent with the bidding
.
if the construction unit adopts retaining wall and sand bag slope protection, should it be included in the settlement cost? ■ Answer: if the project adopts bidding, whether the bidding scheme adopts retaining wall can not be calculated separately
.
for the construction contract of the construction project, according to the total price of the project in the preliminary budget, the labor insurance premium shall be more than 180000 yuan, but both parties agree to lump sum 150000 yuan in the contract
.
If so, it belongs to the scope of claim according to the contract
.
If not, they cannot be increased.
.
The two sides argued and the negotiations reached an impasse
.
The contract is an adjustable unit price contract
.
Later, due to the capital of the construction party, the project was suspended and could not be resumed for up to 18 months
.
the question is whether the 5 million will be charged for measures and regulations? In addition, does the 10% premium of 500000 also record the measure fee and regulation fee? ■ A: the cost of materials and measures provided by Party A are two independent costs, and there can be no relationship between them
.
No matter what causes the change, the fees and taxes shall be adjusted according to the settlement amount
.
Of course, if the settlement amount changes, the fees and taxes should be adjusted accordingly
.
The full hall foundation must be reorganized? ■ A: according to the specific requirements of the contract for settlement items, it is necessary to analyze whether the material price is lump sum and whether the change of the contents of the list items causes the change of measures
.
How should this situation be settled? ■ A: first, the settlement must be in accordance with the contract
.
If not, it cannot be recognized
.
If there are no requirements, both parties shall coordinate and determine the settlement method, but it must not be in accordance with the settlement method for the normal operation of the project
.
The construction party believes that the contract is signed as “lump sum use”, that is, whether the project is increased or reduced, it shall be lump sum of 150000 yuan without adjustment
.