Author: Huang Yingjun, editor of traffic question | Editor in charge: Ji Jia | Editor: Zhao Yu disclosure hotline: 96952 It is recommended to read for another 4 days and have a holiday! Another Mega Bridge is completed! Guizhou infrastructure, yyds! Guiyang shed change new news, involving many places! See if you will become a “relocated household”?..
came to the construction site of the East Second Ring Road again.
Zhang Ting of Guiyang Quanfeng Construction Management Co., Ltd.
The road grade is urban trunk road, the design speed is 60km / h, the standard subgrade width is 36m, and the two-way six lane layout is adopted.
The completion time of the half road closure construction involved in the East Second Ring Road is June 30, 2022.
The total design length of Dongxin road project is 5.86km, of which Dongxin road section is about 4.63km long and Xinli Avenue section is about 1.23km long.
The bridge tunnel ratio of the whole line is about 44%.
When it comes to the construction of Dongxin road in Wudang District, where does it start and end and how long is it? Chen Bin, head of Dongxin road project of Guiyang Communications Group Project Management Co., Ltd., introduced that the Dongxin road road project in Wudang District, Guiyang starts at the middle ring road in the northeast of denggaoyunshan park.
replied to the site shutdown: “the main reason for the site shutdown is that our construction location, especially tubazhai, involves forest land.
Zhang Ting told reporters that the completion time of the whole Dongxin road project is about the middle of 2023.
(click the link to view the report) 👉 After the manuscript was published and broadcast, the construction party took the initiative to contact the column group of traffic radio “traffic questions” and agreed to reply to the problems concerned.
On September 3, the official wechat graphic push of Guizhou traffic radio reported the blocking caused by the closed construction of the East Second Ring Road and no construction on the site, which was reported by many listeners.
On the afternoon of September 6, the reporter of the column “traffic asked” and the project leader of Dongxin road in Wudang district and the owner Guiyang Quanfeng Construction Management Co., Ltd.
There are three interchange nodes in the whole line, including central, Xindong second ring and Xinli Avenue; Two bridges are set, namely Guiyu Wenquan bridge (821m long) and Nanming River Bridge (823m long); A DILIN tunnel (total length 965m) is set.
The line position crosses Shunhai middle road from west to East, intersects Xindong Second Ring Road in the southeast of Shunhai oasis resettlement house plot, crosses Wenquan Road, and is arranged along the north of Shuidong road, Cross Shuidong road and Nanming River to the east of the gas station, and then cross yanshangpo mountain to intersect Xinli Avenue.
If there are no other accidents, the half road closure construction of the East Second Ring Road section we are concerned about can be completed as scheduled on June 30 next year.
It is expected that we will continue the construction at the end of September and early October.” in view of the shutdown, Many people worry that the project suspension will affect the project progress, resulting in the construction of this section can not be completed on schedule.
Click the video below to view the reply from the construction party.
Chen Bin told reporters that the completed Dongxin road will improve the road network planning of Wudang District, close the inner ring of Wudang District, extend westward to connect with the extension line of Lincheng East Road under construction, and extend eastward to connect Beijing East Road and Shanghai Kunming expressway, which is of great significance to the subsequent urban development and space of Wudang district, More importantly, the completed Dongxin road will greatly alleviate the traffic pressure of Xintian Avenue and provide a more convenient choice for friends in and out of Wudang.
Now we are promoting the formalities for forest land construction.