Accident situation: hazard degree of the accident, number and degree of injury of the injured, measures taken, impact degree of the accident, etc.

The contents of pre shift safety education include: the operation environment of the team’s workplace on that day Environment; targeted safety technical measures; safety precautions at work; preventive measures for multiple accidents in the work of this type of work, etc.

5.

Before the hidden danger is eliminated, reliable protective measures must be taken.

The address when asking for help from the first aid center is XXX, indicating the name, telephone or mobile phone number of the person reporting for help.

The rectification of potential accidents shall not be carried out without justified reasons The person in charge of the rectification, in addition to urging the rectification, shall be given economic punishment according to relevant regulations.

If the rectification cannot be carried out on the same day due to the difficulties of materials, funds and personnel, it must be reported to the project manager in writing.

For those engaged in electrical, welding, lifting, building climbing and erection, mechanical driving in the plant For special operation types such as special equipment operation, professional technical training and study of safety rules and regulations must be carried out, and the operation can be carried out only after passing the examination of relevant departments and obtaining the operation certificate, and a review shall be carried out once every two years.

2) safety knowledge education: safety operation procedures of the type of work; basic safety knowledge such as electromechanical equipment and high-altitude operation; basic safety knowledge such as fire prevention, explosion-proof, dust prevention and poison prevention; knowledge of the correct use of personal labor protection articles.

3.

The safety disclosure must explain the key precautions for subdivisional works.

8.

The project organizes safety inspection once a week, led by the project leader.

2.

1、 Project safety inspection system 1.

The rectification of potential accident hazards by the responsible person is not a surprise work.

IV.

Employees shall be regularly educated to carefully implement the safety technical operation procedures and strictly implement the safety technical disclosure.

7.

In case of emergency danger endangering personnel and equipment, the construction shall be stopped immediately, rectified and reported to the superior competent department at the same time.

4.

2.

In case of a class IV major accident, it must be reported to the Engineering Department of the Bureau and the competent leaders of the Bureau in the form of express report within 12 hours.

The responsible person must immediately after receiving the notice The rectification shall be carried out as required without undue delay.

New entrants must receive “three-level safety education” “, the owner can arrange work after passing the examination.

4.

6.

2.

3) safety skill education: be familiar with the professional safety technical knowledge of the type of work and the post.

3.

7.

2、 Project safety disclosure system 1.

After receiving the personnel accident report from the branch or the project leader, the leader and the competent department of the company shall immediately send the leader in charge and professionals to the site to assist in handling the accident and submit a written report within 24 hours Report to the Engineering Department of the Bureau in a face-to-face manner.

The rectification shall be carried out immediately after the conditions are met.

The main contents of safety education: 1) safety ideological education: relevant national safety production policies, laws and regulations; relevant rules and regulations of the enterprise; construction characteristics and safety construction of the enterprise; and the enterprise Typical accident cases, etc.

Before the commencement of unit works, the project manager shall make disclosure to the project management personnel, and safety technical disclosure shall be made at the same time of technical disclosure, so that all management personnel, especially the foreman, can be familiar with the construction characteristics and safety technical measures of the project.

Safety education and necessary practice suitable for new posts and new operation methods must be carried out when new technologies, new machines and tools and new workers are used in construction International operation training, only after passing the examination can they take the post.

3.

The construction team shall regularly organize safety inspection activities, carefully carry out pre shift safety self inspection, and timely solve problems found.

After receiving the casualty accident report, the project leader and relevant personnel shall quickly rush to the accident site, command the rescue of the injured and report to the site at the same time Make a quick response to the safety situation of the accident and prevent the further expansion of the accident before protecting the scene.

Relevant person in charge shall check the implementation of safety technical disclosure and correct illegal operations in time.

7.

The hidden dangers found in the inspection shall be rectified immediately.

The safety inspection shall be carried out in accordance with the standards for safety inspection of Building Construction issued by the Ministry of construction.

The quality safety department shall carry out safety learning for the operators who seriously violate the rules and regulations, and only after passing the examination can they take the post.

1.

(2) Fire accident report content occurrence time: occurrence place: when reporting to the project leader, the specific general position of the fire shall be stated..

Before the commencement of divisional and subdivisional works, the foreman must make a written safety technical disclosure while arranging the construction tasks of subdivisional works.

If they cannot be rectified immediately, the registration, rectification, inspection and cancellation system shall be established, the rectification plan shall be formulated, and the rectification shall be carried out by designated personnel, time and measures.

industrial accident reporting system.

With reference to the current systems of some excellent construction enterprises, the editor summarizes the 9 major safety management systems commonly used on the construction site, hoping to help you improve your safety management.

A.

4.

4.

Organize safety education once a month for the project.

6.

class safety activity system 1 In order to strengthen the safety education of the team, make the team understand the on-site operation environment, enhance the safety prevention ability of construction personnel, and reduce the occurrence of casualty accidents, these Regulations are formulated.

responsibility system for rectification of potential safety hazards.

3、 Safety education and training system 1.

4.

5.

5.

The inspection team is composed of members of quality safety department, equipment department, engineering department, technology department and logistics security department, which is responsible for inspection, summary and evaluation.

After emergency treatment of the accident scene, report to the branch (or company) as accurately as possible in the fastest way The leader in charge and the Department in charge shall report to the leader and the Department in charge of the company immediately.

The leaders of the dispatched office of the bureau shall hurry up Go to the site to assist in handling the accident and report to the Engineering Department of the Bureau within 24 hours.

VI.

V.

contents of accident report: (1) Content, time and place of casualty accident report: when reporting to the project leader, the specific location of the accident must be stated.

1.

It must be institutionalized, regular and inspected every day, and the problems found shall be rectified immediately.

The time of pre shift safety activities is 15 minutes before going to work every morning, and the team leader shall educate the team members.

Safety disclosure is a form of safety education conducted by the relevant person in charge to the construction personnel according to the project characteristics and the operating procedures that should be observed during construction before the commencement of divisional and subdivisional works of unit works.

6.

Cuplock Scaffolding Manufacturers

The safety technical disclosure shall be signed by the participants.

Before the commencement of the new project, organize the construction personnel to study and test the safety work procedures, safety construction management regulations and the safety rules and regulations of the enterprise, and take the post only after passing the examination.

Judge the injured part in time and send it to a professional hospital quickly and selectively to avoid delaying the treatment opportunity.

2.

3.

After an accident occurs in the project of each unit for construction, the branch company shall immediately report to the dispatched office of the Bureau, and correctly decide to report to the local labor department, procuratorate and competent department of work safety.

3.

The contents of pre shift safety activities must be carefully filled in and targeted.

3.

In case of an accident above level III, the branch company shall immediately report to the competent leaders and departments of the company (or the dispatched offices of the Bureau), and the leaders of the company and the heads of relevant departments (or the dispatched offices of the Bureau) shall go to the site to assist in handling the accident immediately.

In case of an accident above level III, the company (the dispatched offices of the Bureau) shall After receiving the accident report, it shall be reported to the Engineering Department of the Bureau and the competent leaders of the Bureau in the form of express report within 2 hours, and the manager of the accident unit shall personally report to the competent departments of the head office and the Ministry of construction within one week.

2.

If the area under the responsibility of the responsible person has a large workload and cannot be completed at one time, it must write a rectification plan and complete it within a time limit after reporting to the project.

2.

After the casualty accident occurs, the injured or relevant personnel at the accident site shall immediately report to the project leader.

The pre shift safety activity records shall be filled in with special forms.

The foreman is responsible for recording and signing the pre shift safety activities; the records of pre shift safety activities are regularly collected and archived by the project safety officer.

At the same time, the branch or the company shall decide to report to the local labor department, procuratorate and the competent department of work safety.

Pre shift safety activities The project safety officer shall be responsible for supervising and inspecting the activities.