Notice on standardizing the construction permit management of underground pipeline works all districts and counties (functional areas) housing and urban rural construction departments, administrative examination and approval service departments and relevant units: in order to further deepen the reform of “release, management and service”, optimize the business environment and strengthen the management of the quality and safety of urban underground pipeline works, according to the measures for the management of construction permit of construction projects (Order No.

II.

The land use approval document issued by the natural resources planning department or the certificate meeting the land use requirements; 2.

(9) the construction fund has been determined, the industrial injury insurance has been handled, the cost of safety protection and civilized construction measures has been determined in strict accordance with the specified proportion, and the payment plan (can be promised) has been provided to the general contractor III.

(6) there is no construction without a construction permit (can be promised).

5) Requirements, the relevant matters regulating the construction license management of underground pipeline projects are hereby notified as follows: 1.

Licensing conditions.

This notice is not applicable to emergency rescue and disaster relief underground pipeline projects.

(4) Have a list of high-risk projects.

(8) If the general construction contractor has been determined and should be supervised according to law, the supervision enterprise has been determined.

Underground pipeline projects with an investment of less than 1 million yuan (inclusive) or a length of less than 150 meters (inclusive) may not apply for a construction license.

Certificate of approval of pipeline project construction by the owner of land use (or land use agreement).

(2) the planning permit for underground pipeline project construction has been obtained.

Documents of approval of pipeline project construction by the corresponding competent department of the industry; 4.

permit procedure the application for construction permit shall be carried out in accordance with the following procedures: (1) the construction unit can use the “government service” column of the official website of Jinan Municipal People’s government( http://zwfw.jinan.gov.cn/ ).

1.

(5) have specific measures to ensure the quality and safety of the project (listed in the application form and the list of high-risk projects).

(7) if the construction site has basically met the construction conditions and needs to collect houses, its progress meets the construction requirements (can be promised).

Before commencement, the construction unit shall apply to the administrative examination and approval service department at or above the county level where the project is located for a construction license in accordance with relevant regulations, and the issuance and quality of the construction license shall be improved Safety supervision shall be handled jointly.

Plastic Nail Plate

When applying for a construction license, the construction unit shall meet the following conditions and submit corresponding supporting documents: (1) The certificate of land use right or the certificate of land use shall be one of the following.

(3) there are technical data meeting the construction needs, and the construction drawing design documents have been reviewed and qualified according to the regulations.

42 of the Ministry of housing and urban rural development), measures for the administration of construction permit of construction and municipal engineering in Shandong Province (LJF [2018] No.

The copy of the planning license for construction land (if the land use unit agrees in writing, only the corresponding planning land license number shall be provided) 3.

The scope of application is to engage in the construction of various underground pipeline projects such as gas and heat in urban roads.