Bidding conditions and procedures for water conservancy project construction

Preparation of bidding documents.

Handle objections to bidding documents.

The bidding documents shall be sold at the time and place specified in the bidding announcement or invitation for bids.

For projects that must be subject to bidding according to law with state-owned funds in a controlling or dominant position, the determination of the bid winner shall comply with the following provisions: (1) the tenderee shall determine the bid winner candidate ranking first as the bid winner.

2.

Have design documents that can meet the bidding requirements, and have signed a drawing delivery contract or agreement with the design unit to meet the construction progress requirements.

02 bidding procedure 1.

Prepare the base bid price and the maximum bid price.

If the bid evaluation and award cannot be completed within the bid validity period, the tenderee shall notify all bidders to extend the bid validity period.

8.

The supervisor has determined.

If the bidder refuses to extend the validity period of the bid, it shall have the right to withdraw the bid security.

4.

(3) After the bid evaluation committee rejects the unqualified bid or defines it as invalid bid, the bid evaluation committee decides to reject all bids due to the obvious lack of competition due to less than 3 valid bids.

The tenderee shall compensate the bidder for any loss caused by the extension of the period of validity of bids, except for the extension of the period of validity of bids due to force majeure.

The tenderee shall reply within 3 days from the date of receiving the objection; Before making a reply, the bidding activities shall be suspended.

Invitation to bid: invitation to bid shall be issued to more than 3 legal persons or other organizations with bidding qualification.

The tenderee may decide whether to prepare the base bid price at its own discretion.

The tenderee may authorize the bid evaluation committee to directly determine the bid winner, or determine the bid winner according to the written bid evaluation report and the sequence of recommended bid winning candidates proposed by the bid evaluation committee.

5.

(5) None of the bid winning candidates has signed a contract with the tenderee.

7.

(3) After receiving the clarification, the tenderer shall notify the tenderee in writing within 1 day after receiving the clarification and modification notice to confirm that it has received the notice.

The tenderee shall not set a minimum bid price limit.

Re bidding.

Determine the successful bidder.

The tenderee shall not hinder the Bidder from obtaining the bidding documents by means of bid filing, setting unreasonable conditions, qualification examination (except prequalification).

5.

If the bidder agrees to extend the period of validity of its bid, it shall extend the period of validity of its bid security accordingly, but may not modify the substantive contents of the bid documents.

If there is a base price for a project subject to tender, the tenderee shall publish it at the time of bid opening.

A bidding project can only have one base bid price.

(2) If the winning candidate ranking first gives up winning the bid, fails to perform the contract due to force majeure, fails to submit the performance security in accordance with the requirements of the bidding documents, or is verified to have illegal acts affecting the winning results, which do not meet the conditions for winning the bid, the tenderee may determine other winning candidates as the winning bidder in order according to the list of winning candidates proposed by the bid evaluation committee, You can also invite bids again.

Preliminary design has been approved.

It is not allowed to take whether the bid price is close to the base bid price as the condition for winning the bid, nor to take the fact that the bid price exceeds the fluctuation range of the base bid price as the condition for rejecting the bid.

(6) The award of bids shall be completed within the period of validity of bids.

If the clarification and modification notice is sent less than 15 days from the bid deadline and affects the preparation of bid documents, the bid deadline shall be extended accordingly.

3.

(5) After the successful bidder is determined, the tenderee shall issue the notification of award to the successful bidder and notify the unsuccessful bidder at the same time.

4.

Foot Eye Anchor

Issue bidding announcement.

2.

Clarify and modify the bidding documents.

(1) In case of any doubt, the tenderer shall request the tenderee to clarify the bidding documents in writing 17 days before the deadline for bidding.

6.

The sale period of the bidding documents shall not be less than 5 days.

If there are less than 3 bidders, the tenderee shall invite bids again.

The implementation and resettlement of permanent land acquisition, temporary land acquisition and resettlement of construction projects have been implemented or have been clearly arranged.

(2) The clarification and modification notice of the bidding document will be sent to all bidders who purchase the bidding document in writing 15 days before the deadline for bidding, but the source of clarification is not specified.

Under any of the following circumstances, the tenderee will invite bids again: (1) there are less than 3 bidders by the deadline for bidding.

The base bid price can only be used as a reference for bid evaluation.

3.

(3) If the order of the bid winner determined by the tenderee is inconsistent with that of the bid winning candidates recommended by the bid evaluation committee, there shall be sufficient reasons, and it shall be reported to the water administration department for the record according to the project management authority.

(4) Before determining the winning bidder, the tenderee shall not negotiate with the bidder on the bid price, bid scheme and other substantive contents.

Potential bidders or other interested parties who have objections to the bidding documents shall raise them 10 days before the deadline for bidding.

The bid winning candidates recommended by the bid evaluation committee shall be limited to one to three, and the order of arrangement shall be indicated.

01 bidding conditions 1.

The base price must be kept confidential.

The source of construction funds has been implemented and the annual investment plan has been arranged.

(2) All bids are rejected after being reviewed by the bid evaluation committee.

Organize site survey and bid preparation meeting.

Source: water conservancy project data management..

(4) Less than 3 bidders agree to extend the period of bid validity.

The notification of award shall be legally binding on the tenderee and the successful bidder.

If a tenderer has a maximum bid price, it shall specify the maximum bid price or the calculation method of the maximum bid price in the bidding documents.