Daily report on shield construction in work area I of phase I of Hefei Metro Line 8

completion of construction progress II.

Weather: sunny, 23 degrees.

  Daily report on shield construction in work area I of phase I of Hefei project line 8, October 3, 2021, Sunday, August 27 of the lunar calendar.

Construction management personnel and equipment investment III.

safety production of each working face of the project site         Commissioning of shield machine on the right line of Hetang Road station, monitoring the completion of installation, installation of trolley shed, installation of shield shell bentonite, commissioning of stairs, installation of four tomorrow’s construction plan and five major events          Installation of 45t gantry crane in the load clearing section..