According to the results of investigation and evidence collection, the law enforcement personnel issued a notice of illegal act and imposed a fine of 5000 yuan on the construction unit Longhua District Water Pollution Control Center for the illegal act of occupying or excavating urban roads within the approved location and area according to the relevant provisions of the regulations on the Administration of road traffic safety of Shenzhen Special Economic Zone.
According to Zhang Gong, engineer of the Construction Department of Longhua District water pollution control center, the second bid of the project was started at the end of last year, and the on-site construction part was started recently.
It is hoped that the construction party will rectify all non-standard places as soon as possible and return citizens to a clean and tidy road! It is also reminded that the construction unit of road related projects should keep in mind the “three requirements” of road administration construction and obtain the permit for legal construction before ▼ construction; During construction, safety enclosure shall be done well and construction shall be standardized; After construction, it shall be restored in time and the aftermath work shall be done well.
It is understood that the construction unit of the project is Longhua District water pollution control center, and the construction unit is Shenzhen Futian Jian’an Construction Group Co., Ltd.
When workers do pavement breaking on the sidewalk, there is no basic safety protection, the site fence is simple, and the warning light is only fixed with iron wire, which is easy to scratch passers-by.
This is the main travel channel for tens of thousands of residents of Longhua Dalang street every day.
“Thursday road recorder” also went to Minqing Road, Longhua District to see the scene.
After the completion of the road, it can greatly improve the traffic environment in Dalang area and alleviate the travel problems of citizens.
Due to construction needs, the enclosure of Dalang North Road project occupies one lane, leaving only one lane for traffic, which makes the already spacious road more and more congested.
[handling results] according to the investigation and evidence collection results, the law enforcement personnel issued a notice of illegal act and imposed a fine of 20000 yuan on the illegal act of the construction and works Department of Longhua District, the construction unit, which did not go through the change approval procedures in advance in accordance with the relevant provisions of the regulations on the administration of road traffic safety of Shenzhen Special Economic Zone.
On Thursday, the road recorder came to Minqing road for a field visit.
The staff of Minzhi Street criticized and educated the construction unit’s disorderly management on the construction site.
Law enforcement departments have zero tolerance for all kinds of illegal road occupation.
Up to now, the road occupation construction permit applied for by the project has expired.
If citizens find illegal construction occupation or traffic safety hazards and congestion hazards in road occupation construction sections, please call twelve thousand three hundred and twenty-eight Do you encounter any trouble caused by digging roads in your daily life? Have you encountered any non-standard construction? “Thursday road recorder” clue collection! Look here for clues! Scan or click the QR code below or stamp the end of the text“.
Let’s see the scene together! It takes half an hour to walk three kilometers! Many construction points of Dalang North Road are not standardized What project is under construction here? According to the public information, in 2017, the municipal engineering of Dalang North Road was listed as the key livelihood project of the municipal government, which was started in August 2018 and planned to be completed and opened to traffic in November 2021.
[handling results] according to the investigation by the law enforcement personnel of the administrative law enforcement detachment of Shenzhen Transportation Bureau, there are problems such as over wide road occupation and non-standard enclosure.
In addition, on the sidewalk on the north side of the road, some people are carrying out construction work, but there is no enclosure on the site, and the Yellow residue is directly stacked on the road.
The road is congested.
Some nearby residents responded that it takes half an hour for a road less than 3km to pass during peak travel in the morning and evening.
This section connects Dalang South Road in the East, Huaning road in the west, Guihua Huasheng road in the South and langrong road in the north, with a total length of about 2.5km.
Recently, the “road recorder on Thursday” received a complaint that the municipal works of Dalang North Road have been occupied for a long time, and there is no construction.
Why does it cause road congestion? Recently, the “Thursday road instrument” went to the scene ▼ Nandu reporter learned that the construction unit of Dalang North Road Municipal Engineering is Longhua District construction and works Department, and the construction unit is the second Construction Co., Ltd.
At the same time, the road surface of the traffic relief section is seriously damaged, and vehicles need to slow down when passing, which also aggravates the road congestion.
Citizens should avoid it when passing by, which has certain potential safety hazards.
However, Nandu reporter found at the construction site that the main works of the road have been basically completed, leaving only ancillary works such as road markings and well covers unfinished.
Nandu reporter saw at the scene that construction was under way in the enclosure on the sidewalk of Minqing road in front of Shenzhen art high school.
Speaking of Dalang North Road Many people should be familiar with it.
There is only one lane to pass.
of China Construction Eighth Bureau.
There are potential construction safety hazards in the road section at the gate of the school.
The iron wire is easy to scratch pedestrians.
Under the supervision of the law enforcement detachment and other departments, the construction unit timely narrowed the road occupation scope and rectified the potential safety hazards of the fence.
How to deal with these problems? ▼ on the same day, the staff of Minzhi street, Longhua District also arrived at the site to urge the construction unit to rectify in time.
This key livelihood project is originally to facilitate citizens’ travel.
What are the problems at the construction site here? ▼ the road near the north section of the school gate has been excavated, and the hook machine is loading mud onto the mud truck.
A number of dump trucks and sprinkler trucks are parked in the reconstructed road in the fence.
Many teachers and students of Shenzhen Art High School found that there are several more construction on Minqing road in front of the school, which has a certain impact on the travel of teachers and students.
The time of road occupation permit is from February 4, 2021 to August 4, 2021.