Next week’s plan: 85% of the holes are blocked, the wall base treatment is completed, and 30% of the slope making layer is completed…
Last week’s plan: The installation of branch and riser is completed, 40% of the hole is blocked, and 30% of the wall base treatment is completed.
The completion of this week: The installation of branch and riser is completed, 40% of the hole is blocked, and 30% of the wall base treatment is completed.