Why hasn’t the road passed when the construction is over? Department response!

Due to diseases, the railway bridge across Longhai needs reinforcement construction.

“The project has been completed, but it is found that there are still diseases on the approach bridge pavement.” Liang Hualin told reporters that the scheduled maintenance and construction have been completed.

Liang Hualin, chief of the maintenance section of Shangqiu highway maintenance center, said that Shangdu Avenue is the name of the section of national highway 105 located in the urban area.

I don’t know when these fences can be removed.

On September 13, Mr.

According to the weather conditions, the weather will clear up in about three days, the pavement will be laid and open to traffic.

On September 28, at the end of the construction, Mr.

On the problems reflected by Mr.

It can only be paved after the weather turns sunny and the pavement is dry.” Liang Hualin said that it takes about four hours to lay a new layer of asphalt pavement, and it will be open to traffic soon without maintenance.

Fences block the road.

Liu said that the construction enclosure of the Longhai railway bridge across Shangdu Avenue had not been removed and the vehicles were still impassable.

Flat End Socket Cross Pin

Before the national day, all construction will be completed and road traffic will be restored.

The line breaking construction time is from August 8 to September 28.

Many passing vehicles have to detour far.

Liu’s help.

Although the conditions for removing the construction enclosure and restoring traffic have been met, there are diseases on the approach bridge pavement not within the scope of this maintenance and construction, and there may be damage and potholes on the approach bridge pavement in the near future, “If we don’t build the approach bridge pavement now, we will have to build it soon.” Liang Hualin said that while the road is still closed, we plan to pave a layer of asphalt pavement on the approach bridge pavement, which can solve the diseases on the road, “A new layer of pavement must be paved on the old pavement without water, but the continuous rainfall in recent days makes it impossible to pave the asphalt pavement.

Liu in the demonstration area asked for help and said that the Shangdu Avenue cross Longhai railway bridge was said to be repaired in August this year, and a construction fence was set, but it was not repaired.

  Source: Beijing Kowloon evening news..

Liu, the reporter contacted Liang Hualin, chief of the maintenance section of Shangqiu highway maintenance center again.

The base reinforcement construction of highway bridges is carried out under the bridge deck, and there are no constructors on the road.

Why hasn’t the road passed when the construction is over? Department response: it was found that the passage of new pavement diseases needs to be delayed for several days.

He said that due to the rainfall and the asphalt pavement of the approach bridge, the time to resume traffic needs to be delayed for several days.

On September 15, this newspaper reported on Mr.