From the regulation of the Ministry of housing and urban rural development that the Ministry of housing and urban rural development plans to adjust the safe and civilized construction cost, the original employer should prepay no less than 60% of the total safe and civilized construction cost of the current year within 28 days after the commencement of the project, but should prepay 50% of the total safe and civilized construction cost to the Contractor within 28 days after the commencement of the project.
144 [2021] from the Department of housing and urban rural development of all provinces and autonomous regions, and the housing and urban rural development (Management) Committee of municipalities directly under the central government, Housing and Urban Rural Development Bureau of Xinjiang production and Construction Corps, construction project cost management organization of relevant departments of the State Council and relevant units: in order to improve the market-oriented formation mechanism of project cost and further unify the project pricing rules, we revised the code for valuation with bill of quantities of construction projects (gb50500-2013) to form the valuation standard with bill of quantities of construction projects (Draft for comments) is hereby sent to you for comments.
Screenshot of relevant regulations on bill pricing in 2013 version: letter from the standard quota Department of the Ministry of housing and urban rural development on Soliciting Opinions on the valuation standard with bill of quantities of construction projects (Exposure Draft) No.
Please feed back your written comments to our company before December 15.
10.2.3 if the employer fails to pay the safe and civilized construction fee on time, the contractor may urge the employer to pay; If the employer fails to pay within 7 days after the expiration of the payment period, the contractor has the right to suspend the construction, and the employer shall be liable for breach of contract.
The Ministry of housing and urban rural development standard ration division recommended the official account of quality in November 17, 2021: friends who need more information can click.
Recently, the Ministry of housing and urban rural development issued the code for valuation of bill of quantities of construction projects (GB 50500-2013) was revised to form the valuation standard of bill of quantities of construction projects (Exposure Draft), The relevant provisions on safe and civilized construction cost are as follows: Screenshot 10.2 of relevant regulations on new bill of quantities pricing Safe and civilized construction cost 10.2.1 the content and scope of use of safe and civilized construction cost shall comply with the provisions of relevant documents and engineering quantity calculation standards of national, provincial and industrial construction competent departments.
Otherwise, the employer has the right to order it to make corrections within a time limit; If it fails to make corrections within the time limit, it may be ordered to suspend the construction, and the increased expenses and / or delayed construction period shall be borne by the contractor.
10.2.4 the Contractor shall make a special fund for the safe and civilized construction cost, which shall be separately listed in the financial accounts for future reference and shall not be used for other purposes.
Contact and fax: Cong Mingxue, 010-58934733 contact email: chengm@mohurd.gov.cn Contact address: standard and quota Department of the Ministry of housing and urban rural development, No.
In the 2013 edition of code for valuation with bill of quantities of construction projects, the relevant provisions on safe and civilized construction cost are that the employer shall prepay no less than 60% of the total safe and civilized construction cost of the current year within 28 days after the commencement of the project, and the rest shall be paid at the same time as the progress payment.
10.2.2 The employer shall prepay 50% of the total cost of safe and civilized construction to the Contractor within 28 days after commencement, and the rest shall be decomposed according to the principle of arrangement in advance and paid at the same time as the project progress payment.