At present, the disposal of old road diseases of the project has been basically completed, and the construction of bridge and culvert works, shoulder widening and drainage works are under way.
Among them, tanglao 1 bridge has completed the construction of the left bridge, and the pile foundation construction of the right bridge is under way; Tanglao 2 bridge has completed the hoisting of the right substructure and precast beam, and the deck pavement is under way; The left deck pavement and approach slab of shuizikou bridge have been completed, accounting for 47% of the total investment of the project.
Jiangmen Enping highway affairs center reminds the public: during the construction period, please drive slowly and safely according to the on-site traffic instructions.
It is expected to be completed in June next year.
According to the person in charge of the construction site, the current season with less rain is a favorable opportunity for construction.
Previously, this newspaper has reported that the construction of the project closed the Sankeng Village section, and passing vehicles need to bypass Zijing street and Enping Avenue.
[source: Enping reporter Station of Jiangmen daily]..
In order to ensure that the project is completed on schedule and with good quality, resume normal traffic as soon as possible, and better serve the broad masses of the people, Enping highway affairs center has made every effort to promote the project construction, seize the favorable days with less rain in autumn and winter, reverse the construction period, and ensure that “construction quality is in place and safety measures are not lax”, forming a working situation of 5 plus 2, white plus black.
Recently, the reporter learned from Jiangmen Enping highway affairs center that the expansion project from Luping village to Jinxiu Jiayuan section of provincial highway 276 yunbei line will scientifically arrange day and night shift construction from November 9, so as to ensure high quality and complete the construction goal on schedule.
The overall project is progressing steadily, laying a solid foundation for the completion on schedule.
Fixing Socket Angular End Nail Plate
Since the official commencement of construction in April, the project has entered the comprehensive construction stage.
For night construction, they scientifically arrange and deploy the construction period arrangement, technical difficulties, atmospheric dust control, construction noise control and construction points according to the characteristics of the night, especially more strictly control the project quality and construction safety, and organize business departments The supervisor and the construction party shall measure and record relevant data at any time to ensure that each working face is inspected in place, and conduct strict safety supervision over the whole construction area and each specific construction point for 24 hours, leaving no dead corner, so as to eliminate the occurrence of safety production accidents.